3.1. Steady-State Analysis
As the water transfer system is in a steady state most of the time that accounts for the majority of energy consumption, the selection of the steady-state working condition has important implications for cost reduction in the operation of the project. Under the fixed water levels, the steady-state operating schemes of three scenarios for the Daxing Branch project are considered, as shown in
Table 3.
Table 3 shows the flow rate of each pipe, the number of running pumps, the running speed of pumps, and the flow rate, head and efficiency of a single pump under five schemes of three scenarios. In scenario OS3, when the pump runs at the rated speed, the maximum flow rate in pipe ③ is 4.15 m
3/s because of the constraints of the minimum operating water level of the regulating tank, which could not satisfy the water demand of the new airport. Therefore, the running speed of the pump should be reduced to reduce the head and flow rate of the pump and increase the water level of the regulating tank. As the running speed of the pump is adjusted to 0.8 of the rated speed, the flow rate in pipe ③ can satisfy the water demand.
When the pump runs at the rated speed under boundary water levels, the flow rate in pipe ① is reduced in scenarios OS2 and OS3 compared to that in scenario OS1 because of the demand flow rate of pipe ③, resulting in a reduction in the head loss in pipe ① and the required head of the pump but an increase in the flow rate of a single pump. As a consequence, the efficiency of the pump is decreased in scenarios OS2 and OS3, which may cause a further increase in energy consumption. The increase in the flow rate of each pump results in an increase in the total flow rate demand of pipe ① and ③, and consequently a decrease in the water level of the regulating tank and an increase in the flow rate of pipe ②.
In scenario OS2, the flow rate demand of pipe ③ can be met whether or not the running speed of the pump is adjusted. The scheme OS2-C2 can increase the amount of water to be transferred. However, as far as energy consumption is concerned, the scheme OS2-C1 is better than OS2-C2. In addition, the steady-state working condition has significant impacts on various transient processes, which should be considered in the selection of steady-state working condition as described in the next Section.
3.2. Analysis of Transient Processes
The steady-state working condition is taken as the initial condition for the calculation of the transient process. Therefore, the following transient processes are analyzed with OS1-C1, OS2-C1, OS2-C2, and OS3-C1 as the initial condition when other pipelines are normally operated, respectively.
D1: The valve V7 is closed in a straight line within 400 s.
D2: All pumps fail and valves behind them are also failed to be closed.
D3: All pumps fail and valves behind them are closed to an angle of 72° within 24 s and fully closed within 120 s.
D4: Pumps are stopped successively and valves behind them are closed to an angle of 72° within 24 s and fully closed within 120 s.
D5: Pumps are started successively and valves behind them are opened in a straight line within 120 s.
D6: The valves V12 and V13 are closed in a straight line within 400 s under OS2-C1, OS2-C2, and OS3-C1.
Then, the maximum (H
max) and minimum (H
min) pressure of the system, the maximum reverse speed (N
max_rev), and flow rate (ν
max_rev) of the pump, the maximum allowable time interval (T
max) with subsequent regulation are shown in
Table 4,
Table 5,
Table 6 and
Table 7.
Under condition D1, the valve V7 is closed, thus leaving only the regulating tank for water supply to pipe ① and ③. As a result, the water level of the regulating tank decreases, and then the head of the pump required to transport water to the South Branch increases and the flow rate of pipe ① decreases. In scenarios OS2 and OS3, the flow rate of pipe ③ also decreases as the water level of the regulating tank decreases.
The flow rate in each pipe and the water level of the regulating tank are shown in
Figure 5. It is found that when OS1-C1, OS2-C1, and OS2-C2 are taken as the initial condition, the water level of the regulating tank drops below the lower limit at 2593, 4604, and 442 s, respectively; whereas when OS3-C1 is taken as the initial condition, the water level reaches a new steady state before dropping below the lower limit.
However, measures would be required if the water level does not reach a new steady state, as shown in
Table 4.
Figure 5b,c shows that when OS2-C2 is taken as the initial condition, there is only 42 s left after subtracting the valve closing time of V12 and V13 since the water level of the regulating tank is only 0.11 m higher than the lower limit. When OS2-C1 is taken as the initial condition, the steady-state water level of the new airport is also high due to the high initial steady-state water level of the regulating tank, resulting in a longer time for the drop of water level to the lowest water level, and the flow rate of pipe ③ is reversed at 1512 s, which slows down the decreasing rate of the water level of the regulating tank. As shown in
Figure 5d, the flow rate of pipe ③ is reversed at 1855 s in scenario OS3. Finally, the reverse flow rate of pipe ③ is equal to that of pipe ① before the water level of the regulating tank reaches the lower limit.
Under conditions D2–D4, no water would be supplied to the South Branch, and thus the supply of water from the Langzhuo Branch causes an increase in the water level of the regulating tank. It is noteworthy that under condition D2, the failure of pumps and valves behind them results in reverse flow from pumps to the regulating tank and consequently a further increase in the water level of the regulating tank. Therefore, the maximum allowable time interval with subsequent regulation is the shortest. As shown in
Table 5, in scenario OS1, the water level of the regulating tank exceeds the upper limit at 1096 s, and the pump is reversed at 143 s. In scenario OS2, when OS2-C2 is taken as the initial condition, the flow rate of pipe ③ increases due to the increase in the water level of the regulating tank. Finally, as the initial steady-state water level of the regulating tank is close to the lower limit, the flow rate of pipe ③ is equal to that of pipe ② when the water level of the regulating tank is lower than the upper limit. When OS2-C1 is taken as the initial condition, the water level of the regulating tank exceeds the upper limit at 2262 s. In scenario OS3, as the flow rate of pipe ① is lower than that of pipe ② and ③, the flow rate of pipe ③ would not be equal to that of pipe ② before the water level of the regulating tank exceeds the upper limit. The transient processes of scheme OS1-C1, OS2-C1, OS2-C2, OS3-C1 under D2–D4 are shown in
Figure 6.
Under condition D5, due to the normal startup procedure is to start the pump first and then open the valve behind the pump, thus the flow rate of pipe ① gradually reaches the required flow rate and the water level of the regulating tank rises slightly before self-balancing.
Under condition D6, the closing of valves V12 and V13 results in an increase in the water level of the regulating tank, and subsequently a decrease in the flow rate of pipe ② and an increase in the flow rate of pipe ①. However, the flow rate of pipe ① is always lower than that of pipe ②, resulting in a continuous increase in the water level of the regulating tank. Finally, as shown in
Table 7, the upper limit is exceeded at 4735, 16003, and 3612 s when OS2-C1, OS2-C2, and OS2-C3 are taken as the initial conditions, respectively. Additionally, the measures should be taken to ensure the water level of the regulating tank to be lower than the upper limit. In scenario OS2, as the steady-state water level of the regulating tank is lower under condition OS2-C2 than that under condition OS2-C1, the maximum allowable time interval with subsequent regulation is longer when OS2-C2 is taken as the initial condition. The transient processes of scheme OS2-C1, OS2-C2, OS3-C1 under D6 are shown in
Figure 7.
In summary, OS2-C1 is better than OS2-C2 in terms of the distribution of allowable time interval with subsequent regulation and operation difficulty under different working conditions.
As shown in
Table 4,
Table 5,
Table 6 and
Table 7, when OS1-C1 is taken as the initial working condition, the maximum pressure is 50.715 m at the back of 3# pump under condition D5, because there is no flow as the pump begins to start; while the minimum pressure is −5.511 m in front of valve V5 under condition D3, which can be attributed to the long distance between valve V5 and pipe ①. When OS2-C1 and OS2-C2 are taken as the initial working conditions, the pressure reaches a maximum of 49.131 and 50.844 m in pipe ② under condition D1 and a minimum of −2.873 and −5.829 m at valve V5 under condition D3, respectively. Comparing OS2-C1 with OS2-C2, the peak pressure of the system is smaller because the water rates of pipe ① and ② are small as the pump speed decreases. Thus, OS2-C1 is better than OS2-C2 in terms of the peak pressure of the transient.
Therefore, considering the energy consumption, the amount of water transfer, the peak pressure and the distribution of allowable time interval with subsequent regulation, OS2-C1 is recommended in scenario OS2.
When OS3-C1 is taken as the initial working condition, the pressure of the system reaches a maximum of 49.931 m in pipe ② under condition D1, and it reaches a minimum of −0.065 m in pipe ① under condition D2. Due to the higher flow rate of pipe ① when OS1-C1 is taken as the initial working condition, the maximum pressure is observed at different positions compared to other initial working conditions.
In the hydraulic transient process under the recommended initial conditions, the maximum and minimum pressure envelopes along the pipelines are shown in
Figure 8. It is found that the extreme value of pressure in the transient process meets the safety requirements.
3.3. Analysis of Coupled Operation of Pumps and Valves
A complex water transfer project with multiple water sources and users often requires coupled operation of devices to achieve the switching of working conditions. Although the peak pressures caused by the switching of steady-state working conditions at different periods are lower than that caused by opening/closing valves or pumps or mechanical failure of a device because of small changes of the flow rate, the time required to reach the new steady-state working condition (Tnew_steady) and the sequence and the time interval of the coupled operation of pumps and valves have important implications for actual operation.
Taking the switching from scenario OS1 to scenario OS3 as an example. As shown in
Table 8, this can be achieved in three steps: 2# and 3# pumps are stopped, the speed of 1# pump is adjusted to 0.8 of the rated speed and opening of valves V10 and V11 in a straight line within 60 s. Since all pumps are in the same pump station, only the sequence of stopping pumps, opening valves, and simultaneous regulation are considered. The time interval between two operations is set to 600 s.
The superposed water hammer pressure has negligible effects since pumps and valves to be regulated are located in different pipelines connected via the regulating tank. The water level of the regulating tank varies slightly, as shown in
Figure 9a. However, it is difficult to achieve precise synchronization during the regulation, and thus the impact of the regulation sequence is analyzed. The results show that the regulation sequence appears to have no significant effects on the water hammer pressure, but it can substantially affect the water level of the regulating tank. For the control scheme RC13-2, the water level of the regulating tank decreases at first because of the opening of valves V10 and V11 and the increase in the flow rate of pipe ③. As a result, the flow rate of pipe ③ increases at first and then decreases until pumps are stopped, after which it increases again. The water level of the regulating tank increases until the steady-state working condition of scenario OS3 is reached at 3891 s. For the control scheme RC13-3, the water level of the regulating tank increases at first because of the stopping of 2# and 3# pumps and the decrease in the flow rate of pipe ①. The water level of the regulating tank increases until the closing of valves V10 and V11 and the flow rate of the pipe ③ increases. The water level of the regulating tank decreases until the steady-state working condition of scenario OS3 is reached at 10905 s.
Given the different trend of the water level of the regulating tank during the transient, it is necessary to analyze the maximum allowable time interval.
Table 8 and
Figure 9b show that if only valves V10 and V11 are opened for the control scenario RC13-2, the water level of the regulating tank would gradually decrease until a new steady-state condition is reached at about 5000 s. However, if only 2# and 3# pumps are stopped for the control scheme RC13-3, the water level of the regulating tank would exceed the upper limit at 2712 s. If the speed of 1# pump is adjusted to 0.8 of the rated speed, the flow rate of pipe ① will further decrease and thus the water level of the regulating tank will exceed the upper limit more rapidly. For these reasons, the control scheme RC13-2 is recommended in this study.