Next Article in Journal
Co-Production of Olefins, Fuels, and Electricity from Conventional Pipeline Gas and Shale Gas with Near-Zero CO2 Emissions. Part I: Process Development and Technical Performance
Next Article in Special Issue
Simulation of Distributed Generation with Photovoltaic Microgrids—Case Study in Brazil
Previous Article in Journal
Innovative Nuclear Energy Systems: State-of-the Art Survey on Evaluation and Aggregation Judgment Measures Applied to Performance Comparison
Previous Article in Special Issue
Enhanced Load Power Sharing Accuracy in Droop-Controlled DC Microgrids with Both Mesh and Radial Configurations
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Utilization of Electric Vehicles and Their Used Batteries for Peak-Load Shifting

Solutions Research Laboratory, Tokyo Institute of Technology, 2-12-1 Ookayama, Meguro-ku, Tokyo 152-8550, Japan
*
Author to whom correspondence should be addressed.
Energies 2015, 8(5), 3720-3738; https://0-doi-org.brum.beds.ac.uk/10.3390/en8053720
Submission received: 23 February 2015 / Revised: 21 April 2015 / Accepted: 24 April 2015 / Published: 30 April 2015
(This article belongs to the Special Issue Microgrids)

Abstract

:
The utilization of electric vehicles (EV) and their used batteries in supporting small-scale energy management systems were studied. Both theoretical study and practical demonstration were performed to measure the feasibility of the developed system. Each five EVs and used EV batteries were used along with 20 kW photovoltaic (PV) panels as a renewable energy source. The main objective of the developed system is performing a peak-load shifting by utilizing EVs, used EV batteries and PV panels. The planning of load leveling was performed 24 h ahead for each 30 min period. The studies showed that the application of EVs and used EV batteries in supporting certain small-scale energy management systems is feasible. In addition, some findings during the demonstration test were listed and analyzed for the purpose of further system development and deployment.

Graphical Abstract

1. Introduction

It has been well known that the deployment of electric vehicles (EV) can reduce greenhouse gases emission and fossil fuel consumption. In addition, the development of EV was accelerated due to rising oil and gas prices, advances in battery technology, etc. [1,2]. Unfortunately, EV still faces some constraints including high investment cost, long charging time, and short driving range. Although the running cost of EV is lower than the conventional vehicles with internal combustion engines, the production cost of EV is significantly higher [3]. Therefore, a value-added utilization of EV is required to increase its economic performance. In addition, large-scale deployment of EV will influence significantly the power system, especially when the uncontrolled charging and discharging are at a high rate. To overcome this kind of problem and increase the economic benefit of EV, the concept of vehicle to grid (V2G) has been developed [4].
The utilization of EV in supporting the grid electricity has been studied previously by many researchers [5,6,7,8,9]. This utilization is possible as both charging and discharging behaviors are controllable leading to the possibility for scheduled charging and discharging. Hence, the parked and plugged EVs can be considered as a potential battery having capability to absorb, store and return the electricity from and to the grid, respectively. V2G can be realized in case three essential requirements are fully fulfilled: (1) electricity connection between EV and grid; (2) communication facilitating control flows between EV and operator; and (3) metering system providing fair measurement [10]. In this V2G system, certain grid operator or energy management system (EMS) can send a request for power to a number of parked and plugged EVs to feed their electricity to the grid or conversely to store the electricity from the grid.
V2G allows several ancillary services to the grid including load leveling, spinning reserve, and storage [11,12]. The distributed EVs also offer a massive energy storage that could be utilized to balance the fluctuating supply [13,14]. In addition, as EVs are mobile, they can be utilized as energy carrier delivering the electricity in different places and time due to price difference or emergency condition. From an economic point of view, the utilization of EVs in V2G is feasible as the estimated profit is higher than the current market price of EV batteries although considering the wear of battery. This analysis has been validated using an actual cycle life data of EV battery cells [15].
It is well known that the battery covers the largest share of the total cost of EV. As the number of EVs increases, the quantity of their used batteries increases accordingly. EV battery is generally replaced once its storage drops to about 70%–80% of its initial capacity because the possible driving range becomes shorter [16]. Hence, although these used EV batteries are not suitable anymore for EVs, they can be utilized as stationary energy storage. This utilization can improve the overall economic efficiency of EV and decrease the environmental impacts due to longer battery end-of-life [17,18]. The concept of used EV batteries reutilization as stationary battery supporting EMS or grid has been reported in some previous works [19,20].
Unfortunately, although many theoretical studies related to both EVs and used EV batteries have been reported, there is a lack of study reporting on real application results. Hence, this study focuses on the utilization of EVs and used EV batteries to support the electricity in certain small-scale EMS covering both theoretical and practical studies. However, as many papers have reported on theoretical analysis, this paper will focus mainly on the report of our demonstration tests and their analyses.

2. EV Utilization for Grid Support

2.1. Community Energy Management

In Japan, to achieve a resilient and smart community especially related to efficient energy usage and reduction of CO2 emission, the concept of community energy management system (CEMS) has been introduced and discussed. The initiative of CEMS comes from the need for harmonization between optimal energy services, potential economy and environmental benefits. CEMS manages the overall energy supply and demand across the community. Basically, it maintains the optimal energy balance in the community with the goal of improving the comfort, safety, security of community members as well as reducing the social costs and environmental impacts. Hence, in CEMS, energy and information streams are flowing simultaneously throughout the community including supply, distribution, storage and consumption. CEMS collects and manages the information and delivers it within the community. It must be robust and highly secured as it handles some personal and authentication information.
CEMS plays as a core of efficient energy utilization throughout the community by communicating the information with other systems both inside and outside of the community. Figure 1 shows the possible structure of CEMS with both electricity and control streams. Inside the community, CEMS collects and manages the information from its lower entities including the building energy management system (BEMS), house energy management system (HEMS), and factory energy management system (FEMS). Outside the community, CEMS has a communication with other CEMS and upper energy providers such as utilities. CEMS will forecast the energy supply and demand which is basically based on historical data and weather forecasts and also calculates the most optimal energy balance to achieve the lowest energy cost within its community. Furthermore, in case of emergency, CEMS will evaluate and control the energy flows and communicate to its lower entities and negotiate with other CEMS or utilities to cover its energy demand.
Figure 1. Possible structure of CEMS (community energy management system) including both electricity and control lines.
Figure 1. Possible structure of CEMS (community energy management system) including both electricity and control lines.
Energies 08 03720 g001

2.2. EV Utilization Schemes

Due to the characteristics of EVs, they can be utilized in supporting the grid electricity as energy storage and ancillary services. As energy storage, EVs can be charged when the electricity price is low due to surplus electricity such as renewable energy (RE) and excess power. In addition, the ancillary services from EVs to the grid could include frequency regulation and spinning (synchronous) reserve. These services are necessary to maintain the grid reliability or to balance the supply and demand. Figure 2 shows the possible utilization schemes of EVs in supporting the grid electricity. Basically, the utilization of EVs in the electricity market can be performed through two types of contract: direct and aggregator-based contracts. A real time data collection in a certain frequency from EVs including state of charge (SOC), position and estimated arrival time is conducted by vehicle information system (VIS). VIS may be owned and operated directly by EMS, aggregator or it is independent as service operator providing EV information to EMS and aggregator.
Figure 2. Possible utilization schemes of EV to support grid electricity: (a) direct utilization scheme; (b) aggregator-based utilization scheme.
Figure 2. Possible utilization schemes of EV to support grid electricity: (a) direct utilization scheme; (b) aggregator-based utilization scheme.
Energies 08 03720 g002
In direct contract, the EV owners have the service contract directly with electricity-related entities. In this scheme, both the electricity and information are handled privately. Hence, it is well-suited for a relatively small-scale EMS, such as BEMS and FEMS, and in where EVs are parked and connected for a relatively long time, for example during working hours. The main benefit of this scheme is that it could maximize the profit of the involved entities. In addition, the charging and discharging controls are easier to use, as EVs are directly connected and fully controlled by EMS. The current study focuses on this type of utilization scheme.
On the other hand, in an aggregator-based contract, EV owners have service contracts with the aggregator. Hence, there is no direct contract between EV owners and EMS or other electricity-related entities. The information including its position and battery condition is basically handled by aggregator via VIS. Furthermore, aggregator will negotiate for electricity business with the electricity-related entities such as EMS or electricity utilities. This kind of utilization scheme is prevalent for relatively large-scale EMS or electricity utilities. EVs which are taking part in the offered ancillary service programs may be distributed in different locations, such as charging stations and parking areas. The electricity to and from EVs may be transferred via power wheeling system through the available transmission and distribution grids. Aggregator offers some possible ancillary services to the EV owners. In turn, EV owners can choose them and receive their profit payment from aggregator.
Load leveling correlates strongly with the management of both demand and supply of electricity. Its aim is lowering the total power consumption in peak hours by shifting the load from peak to off-peak hours. Load leveling can be performed through peak-shift and peak-cut. Peak-shift is defined as moving the electricity load during peak time to off-peak time. It could be achieved through utilization of stationary battery or other power storage devices. On the other hand, peak-cut is defined as the effort to reduce the electricity purchased from the grid by generating or purchasing the electricity. In reality, it could be performed through harvesting the energy especially during peak hours, such as RE, or by purchasing the electricity from other entities including the plugged EVs. In this case, EV is considered as energy storage and carrier which is storing and transporting the electricity from different times and places. Hence, the economic performance of EV can be increased by joining this kind of ancillary program.

2.3. EV Integration to Small-Scale EMS

The schematic diagram of integration of EVs and their used batteries to support the electricity in a small-scale EMS is shown in Figure 3. In this study, small-scale EMS includes BEMS, FEMS, and HEMS. EMS basically controls all the electricity demand and supply. It requests, manages, and integrates some information from difference sources: its own load, meteorological agency, VIS, CEMS, and utility. EMS has a contract with a meteorological agency who provides the local weather information. Therefore, the meteorological agency sends the weather information for a certain period of time during a day. This weather information is used by EMS to forecast its own load and the potentially generated electricity from RE. The type of building load basically can be categorized into base load and fluctuating load. The base load is the minimum amount of electricity demand to power the system operating for 24 h continuously. The base load is generally constant along the time and not influenced by the weather. On the other hand, fluctuating load depends strongly on the human behavior, which in turn, is influenced by the weather condition including temperature and humidity. In addition, the available RE, such as wind and solar, which can be generated, is forecasted also by EMS based on received weather information.
Figure 3. Basic schematic diagram of EVs and their used batteries integration to EMS.
Figure 3. Basic schematic diagram of EVs and their used batteries integration to EMS.
Energies 08 03720 g003
Figure 4 shows the seasonal average total load for office building, especially in Japan. The highest total demand occurs in summer, and is followed by one in winter. Both loads in spring and autumn are almost similar and lower than winter. In addition, daily peak-load occurs twice in a day: before noon and afternoon peak-loads. This is due to the sudden drop of electricity demand during a 1 h lunch break. Compared to before noon peak-load, the afternoon peak-load takes place over a relatively longer time (almost 3 h) and has a higher value. In addition, the highest peak-load in summer occurs during afternoon time starting from 13:00 to 16:00. On the other hand, the highest peak-loads in winter, spring, and autumn take places in the evening time between 16:00 and 17:00. This phenomenon is considered to be influenced strongly by the demand for air conditioning in each season.
Figure 4. Seasonal average load for office building.
Figure 4. Seasonal average load for office building.
Energies 08 03720 g004
EMS also receives the EV information from VIS consisting of its position, SOC, and estimated arrival time. VIS monitors and gathers the information from its EV member wirelessly. VIS can be an independent service operator or a part of EMS or aggregator. It is responsible for communicating with each EV and providing the data to the EMS or aggregator. Furthermore, this data is used for coordination of EV charging/discharging and to maintain the balance of electricity distribution and avoid any peak-load in EMS. On the other hand, VIS also can provide additional services to the driver regarding the availability of ancillary service programs which are being offered by EMS or aggregator. In addition, EMS also requests from an electric utility the electricity condition and price information. This will be used to calculate the demand as well as the charging and discharging behaviors of both EVs and used EV batteries.
EMS can control fully the used EV batteries and plugged EVs. Therefore, EMS cannot control the EVs which are not connected to the designated charging poles. It only receives the information from VIS without the capability to control the remotely moving EVs. Figure 5 shows the assumption of a one day specific curve of SOC state during a weekday. EVs are departed in the morning and reach the target building at around 9 AM. Because the afternoon peak is higher and the available electricity from EV is relatively limited, EVs are basically utilized for peak-cut in the afternoon peak-load. Discharging from EVs ends once the peak-cut finishes or their SOC reaches a certain minimum value (SOCmin) which can be defined by the owner, EMS, or aggregator. Furthermore, EVs leave the office at around 6 PM with SOC in minimum condition (SOCmin). When the total building load—which is an original demand of the building to operate or facilitate the activity inside the building—is relatively low (such as in the morning and during a lunch break), EVs may be charged to increase their discharging capacity during peak time.
Figure 5. The assumed SOC state of EV for 24 h during a weekday.
Figure 5. The assumed SOC state of EV for 24 h during a weekday.
Energies 08 03720 g005
To join the ancillary services offered by EMS, the EV owner must have a contract with EMS whether direct contract or through third entity such as an aggregator (aggregator-based contract). Due to the mobility of EVs, their charging and discharging are controlled by EMS only when they are connected to the charging poles. On the other hand, the used EV batteries are fixed and always connected directly to EMS. Hence, their charging and discharging behaviors are fully controlled by EMS. Used EV batteries are basically used for peak-shift. They are charged during the night with a cheaper electricity price and discharged during peak time to decrease the electricity demand from the grid.

3. Proposed Utilization System for EVs and Their Used Batteries

Figure 6 shows the basic concept of load leveling developed for a small-scale EMS utilizing EVs, used EV batteries and RE including photovoltaic (PV) and wind. Four main continuous steps were proposed in this study: (1) RE generation and load forecasting; (2) load leveling forecasting; (3) value correction; and (4) charging and discharging controls of EVs and used EV batteries. The forecasting was basically performed by EMS for 24 h-ahead. In addition, because the amount of electricity in Japan is basically calculated for every period of 30 min, all electricity amounts (kWh) in this study were calculated as the total accumulation value for 30 min.
In RE generation and load forecasting, EMS initially requests information related to local weather forecasts from the meteorological agency. This information is very important in order to calculate the possibly generated electricity from RE including PV and wind. In this study, this generated electricity is prioritized in peak-cut and will be consumed entirely with no storage. In addition, the weather information is also utilized to predict the fluctuating load of the building, especially related to air conditioning and lighting. The outputs from this first step are forecasted RE generation and load curves for the next 24 h.
Once the load and RE generation have been forecasted, EMS calculates the possible load leveling which can be achieved in the next 24 h. For this purpose, EMS communicates with VIS to estimate the number of EVs and their SOC states which are available to join the peak-cut program. VIS initially receives the travelling schedule from the drivers and, subsequently, VIS transfers this information to EMS. This information includes the EV’s ID, planned departure time and estimated arrival time. Moreover, the registration of travelling schedule by the driver/owner should be done up to 24 h before the scheduled departure. As the available resources for peak-cut/peak-shift and load curves were estimated, EMS can calculate the peak-cut threshold for the next day. In this study, peak-cut threshold is defined as the maximum amount of electricity purchased from the grid by EMS. Peak-cut threshold is theoretically calculated based on some factors including electricity price, contracted capacity, available power generation, and storage. When the electricity consumed by the building is increasing and the purchased electricity from the grid reaches the peak-cut threshold, EMS sends the command to plugged EVs and used EV batteries to discharge their electricity to support EMS. Hence, the electricity purchased from the grid is same to of lower than the calculated peak-cut threshold. In the real application, it may avoid a higher price of electricity during peak time.
Figure 6. Basic concept of developed load leveling in a small-scale EMS involving EVs and their used batteries.
Figure 6. Basic concept of developed load leveling in a small-scale EMS involving EVs and their used batteries.
Energies 08 03720 g006
When EVs are departed or in motion, the information related to EV is transmitted to VIS in intervals of several seconds to minutes for data updating. Afterward, VIS sends the data to EMS which is further used to recalculate the available electricity from EV. On the other hand, EMS also recalculates the building load based on the real weather, measured by thermometer and hygrometer, and the present real load of the building. Next, EMS modifies its energy management plan, especially the predicted peak-cut threshold.
When EVs arrive and they are connected to the designated charging poles, EV can communicate directly with EMS (bypassing VIS). Hence, all the information of EV is updated again including the available electricity from EVs. From this moment, EVs are ready to take part in the ancillary service program offered by EMS. EVs are fully controlled by EMS, especially their charging and discharging behaviors. Finally, EMS calculates and sends the control command to each EV and used EV batteries to maintain its previously calculated peak-cut threshold. After finishing the peak-cut, EMS can control and coordinate EVs for charging before leaving the building.

4. Demonstration Test Bed

Figure 7 shows the schematic diagram and overview of the whole developed demonstration test bed used in this study. Black solid and blue dotted lines represent the electricity and information lines, respectively. This demonstration test bed was built in the area of Mitsubishi Motors Corporation located in Okazaki, Aichi prefecture, Japan. The test bed was connected to and used to support the electricity of the main office building.
Figure 7. The developed demonstration test bed: (a) schematic diagram of the system; (b) overview of the developed system including PV panels and EVs.
Figure 7. The developed demonstration test bed: (a) schematic diagram of the system; (b) overview of the developed system including PV panels and EVs.
Energies 08 03720 g007
As RE generator, 20 kW PV panels were installed on the roof top of the test bed. Five EVs, Mitsubishi i-Miev G, were taking part in the program and the drivers were also the employees working in the office building. Hence, EVs were mostly parked and plugged to the charging poles during the working hours. In addition, five used EV batteries, which were used for about one year from the same type of EV, were also installed and directly connected to EMS. EMS controlled all the demand and supply sides of the test bed. On the other hand, VIS was also developed as a standalone system communicating with EVs and transferring to EMS. The detailed specifications of developed demonstration test beds are shown in Table 1.
Table 1. Specifications of developed demonstration test bed.
Table 1. Specifications of developed demonstration test bed.
ComponentPropertiesValue
PVTypeMono crystalline
Capacity20 kW
Installation direction and angleSouth, 30°
PCS capacityAC 200 V, 100 A
EVsTypei-Miev G
Participating number5
Battery capacity16 kWh
Max. charging capacityDC 370 V, 15A
PCS capacityAC 200 V, 15 A
Used EV batteriesOriginal EVi-Miev G
Condition1 year usage
Installed number5
Battery capacity16 kWh
Max charging capacityDC 370 V, 15A
PCS capacityAC 200 V, 15 A
The drivers sent their travelling schedule to VIS up to one day before the departure. For this purpose, a web-based system has been developed allowing the drivers to access from their computers or mobile devices. When EV was not plugged in the charging pole of EMS, EVs sent their data to VIS in interval of 10 s remotely. Furthermore, VIS transmitted the data to EMS in a real time. Moreover, the used EV batteries became a part of EMS (stationary) and were fully controlled by EMS throughout a day. EMS was receiving data from both VIS and the meteorological agency. Although the weather information was received a day before, it was updated automatically up to three times a day according to the change in the weather forecast.
Used EV batteries were practically utilized for peak-shift. They were charged during the night time (off-peak hours) when the price of electricity is cheaper. In this study, this charging was basically conducted from 00:00 to 06:00 on the next day. The charging and discharging thresholds of both EV and used battery were fixed at SOC 90% and SOC 40%, respectively. Moreover, as the total amount of available electricity from EVs and used EV batteries was very small compared to the total load of the office, peak-cut was designed to start from 12:00 until 18:00 (6 h duration). Hence, the afternoon peak became the main target in this study. Furthermore, to minimize the influence of temperature on charging and discharging behaviors of used EV batteries, the temperature of battery storage room was controlled and maintained throughout the year at 25 °C.
In RE generation forecasting, as only PV was used as RE generator, the generated electricity from RE, PRE, could be approximated as follows:
P R E = P P V = ( H × η P R × C P V ) ÷ I
where, Ppv, Ht, ηPR, CPV, and I are generated electricity from PV (kWh), forecasted average solar radiation in the designated time (kWh m−2), average performance ratio of PV panels, PV system capacity (kW), and solar radiation intensity in standard state (kW·m−2). The forecasted average solar radiation was received from the meteorological agency and updated three times in a day. In addition, building load was approximated as the sum of the base load and air conditioning demand based on statistical data and the forecasted outside temperature received from the meteorological agency [21]. A simplified mathematical representation of the building demand in certain time, Lt, could be represented as follows:
L t = L B S + f ( [ T O A T S T ] t ( Δ τ ) )
where, LBS, f, TOA, TST, and ∆τ are building based load for 30 min interval (kWh), chosen functional relationship, outside temperature (°C), set room temperature (°C), and time shift (h), respectively.
The available electricity from EVs, PEV, which are running and not connected to the charging poles could be approximated as the function of SOC and the remaining distance (both of them are received from VIS).
P E V , t = ( S O C E V , t × C E V d t × η E V ) S O C min × C E V
where, SOCEV,t, CEV, dt, ηEV, and SOCmin are SOC of EV at certain time, capacity of EV battery (kWh), remaining distance to charging pole (km), EV power consumption (kWh·km−1), minimum SOC threshold for discharging, respectively.
Due to some limitations, the peak-cut threshold in this study was calculated with consideration of available sources capacity. This includes average PV generation and available electricity from both EVs and used EV batteries. Initially, a day load duration curve was created based on the average load data in the same month of the last year. Peak-cut threshold, Pthr, was calculated according to Equation (4). The illustration of a day load duration curve and calculation of peak-cut threshold are shown in Figure 8.
f o r L n > P t h r Σ L n = n P t h r + Σ P e v , m + Σ P b a t , m + P p v
where, Pbat, n, and m are available power from used battery, number of load higher than peak-cut threshold, and number of EVs and used EV batteries, respectively.
Generally, load duration curve illustrates all loads in a descending order of magnitude and the area under load duration curve shows the energy consumed by the system. In case of this study, a day load duration curve was adopted and created by arranging all 30 min periods of building load in a downward order from the highest to the lowest loads. Hence, the area under the curve represents the total energy demand consumed by the building for a day. Moreover, the generated electricity from PV was directly supplied to EMS without being stored in the battery. Furthermore, the total electricity which could be earned from EVs, used EV batteries, and PV were plotted on the top of the curve while its bottom is in straight line. The created straight line is a peak-cut threshold which was used in peak-shift and peak-cut.
Figure 8. Load duration curve and the calculated peak-cut threshold.
Figure 8. Load duration curve and the calculated peak-cut threshold.
Energies 08 03720 g008

5. Results and Discussion

5.1. Load Leveling Experiment

Figure 9 shows the results of load leveling test in a representative weekday consisting of total grid load, building load, PV generation, and charged/discharged electricity to and from EVs and used EV batteries. The grid load is the net electricity purchased from the grid. Light green blocks in positive and negative sides represent discharge and charged electricity amount from and to EVs and used EV batteries, respectively. The main objective of peak-cut and peak-shift is to reduce the grid load, especially during peak hours, to reduce the total electricity cost of the building.
Figure 9. Load leveling test on a representative weekday.
Figure 9. Load leveling test on a representative weekday.
Energies 08 03720 g009
PV is generating the electricity during a day and it was directly consumed without being stored. The used EV batteries were charged during the night with a lower electricity price, starting from 00:00 to 06:00. As a result, the grid load during the night slightly increased. In the morning, at around 08:00, EVs reached the office building and they were plugged in designated charging poles. From this moment, charging and discharging behaviors were fully controlled by EMS. Because the building load was still smaller than the calculated peak-cut threshold, charging for EVs was performed until the building load reaches nearly the peak-cut threshold. In addition, additional charging started again during the noon break (12:00–13:00) because the building load dropped drastically.
From Figure 9, it could be observed that peak-load occurs twice: before and afternoon, respectively. However, the peak at the morning time was lower than the one at the afternoon time. In this study, due to limitation of the available EVs and used EV batteries, peak-cut was performed targeting for the afternoon peak-load. Hence, during the morning until 12:00, peak-cut was only performed by the electricity generated by PV panels. Furthermore, the afternoon peak usually started from 13:00 following the end of noon break. As the peak-load reached the value higher than the calculated peak-cut threshold, EMS sent the control command to both EVs and used EV batteries to discharge their electricity. As a result, the grid load could be reduced. Unfortunately, because the total capacity of electricity from EVs and used EV batteries was very small compared to the total building load, peak-cut could only be conducted in a relatively short duration of time. It is believed that as the number of EVs participating in this load leveling program increases, the effect of load leveling could be achieved more significantly. Therefore, a longer peak-cut (including both before and afternoon peak-loads) and lower peak-cut threshold could be achieved accordingly.
In addition, the average SOC pattern in a day for both EVs and used EV batteries can also be observed in the same figure. Used EV batteries are only utilized for peak-shift, hence, its SOC decreases during peak-hours (discharging) and increases during the night (being charged). On the other hand, the SOC pattern for EVs is basically following the pattern in Figure 5. After arriving and being plugged to charging poles, EVs are charged because the building load is lower than peak-cut threshold.
Figure 10 shows the amount of total peak-cut in a day by each PV, EVs, and used EV batteries for the eight-month duration of the experiment. In addition, Figure 11 shows the average total peak-cut by each PV, EVs, and used EV batteries in different months. The used EV batteries have the largest and most stable peak-cut share compared to EVs and PV. The used EV batteries are basically owned directly and also controlled fully by EMS. On the other hand, the generated electricity from PV is influenced strongly by the weather condition and it is fluctuating. In addition, the share of EVs in peak-cut strongly depends to their battery condition (SOC), which in turn, is influenced by their usage in vehicles.
The uncertainties come mainly from three different factors: EV, PV, and building load. They lead to divergence among the planned and real values. In this study, because the capacity of building load is significantly larger than the total electricity from PV, EVs, and used EV batteries, it is considered that the fluctuating load of the building becomes the largest factor causing this uncertainty. In addition, generated electricity from PV is also fluctuating frequently as it depends strongly on the solar intensity.
As a result of this study, although the divergence among planned and real building loads is relatively high, the divergence among planned and real grid loads is relatively low. The divergences in factory load and generated PV are minimized by the charging and discharging amounts from both EVs and used EV batteries. Moreover, in this study, as the drivers of EVs are basically the employees working in the building and the travelling routes are almost constant, the uncertainty regarding EV availability and its capacity did not show any significant impact. It is considered that although the uncertainty regarding EVs’ availability and capacity exists, the divergence among the planned and real grid loads can be minimized as long as the capacity of the used EV batteries which are owned by EMS is enough to support those fluctuating factors.
Figure 10. The amount of peak-cut and peak-shift in a day by each PV, EVs, and used EV batteries.
Figure 10. The amount of peak-cut and peak-shift in a day by each PV, EVs, and used EV batteries.
Energies 08 03720 g010
Figure 11. Average total load leveling by each PV, EVs, and used EV batteries in different months.
Figure 11. Average total load leveling by each PV, EVs, and used EV batteries in different months.
Energies 08 03720 g011

5.2. Discharging Capacity

Figure 12 shows the correlation between total SOC change and the discharged electricity from both EVs and used EV batteries on each weekday for the 8-month duration of the experiment. Discharging was conducted from SOC 90% to SOC 40%, and the capacity measurement was performed at AC output point of power conditioning system. The correlation between SOC change and discharged electricity shows a high linearity. The discharged electricity was almost concentrated in the range of 40–60 kWh with the largest total discharged electricity reached about 60 kWh.
Theoretically, the correlation between SOC change and total discharged electricity is linear. Unfortunately, it is scattered due to some factors including charging and discharging conditions, capacity degradation, and PCS efficiency. It is important to note that to measure accurately the SOC is very difficult. The measured SOC value was based on the information earned from EV control system without an independent measurement conducted by a complete charging and discharging or resistance spectroscopy. Furthermore, capacity degradation and impedance augmentation of lithium-ion battery is also very complicated. It is not only brought about by a single cause, but from various processes and their interactions [22]. However, charging and discharging cycles of battery are considered as the important factor leading to battery ageing. These cycles are mainly related to the number of cycles and the depth of discharge [23]. Capacity degradation influences the driving distance as well as decreasing the discharged capacity during ancillary services [24].
Figure 12. Correlation of total SOC change to the total discharge electricity from both EVs and used EV batteries.
Figure 12. Correlation of total SOC change to the total discharge electricity from both EVs and used EV batteries.
Energies 08 03720 g012

5.3. Problems, Findings and Suggestions

From the conducted studies and demonstration test, there are some important and challenging points related to V2G application in supporting the electricity of a grid or EMS. They are listed as follows:
  • An accurate demand forecast is very crucial to calculating the peak-cut threshold. This demand forecast is not only influenced by the weather conditions, but also the human behavior of the residence. Hence, the database and knowledge about the specific behavior patterns of the residence are very important as they will be different from one place to another. If the behavior patterns are very difficult to grasp, the appropriate method for guiding the behavior of the residence by setting regulations or policies can be selected.
  • To improve the fairness and transparency, the metering of both charging and discharging amounts by trusted third party is essential, especially in the aggregator-based utilization scheme.
  • As the number of participating EVs is increasing, the available capacity for peak-cut also increases accordingly. Unfortunately, as the number of participating EVs increases, more accurate forecasting and calculation of available capacity from EVs are required. In addition, a larger capacity of used EV batteries (stationary batteries) is important to buffer the divergence between the forecasted and real values.
  • In case some participating EVs suddenly stop their discharging service and require charging due to driving distance that will be travelled, EMS also should be able to coordinate the charging behavior of EVs. Otherwise, the uncontrolled charging will cause another peak-load of the building.
  • Although the peak-load in winter is lower than one in summer, peak-load in winter is generally characterized by its occurrence at a late time (evening around 17:00) due to air conditioning demand. As the working time also ends at this time, some EVs are leaving the building or requesting a charging before leaving. EMS should be able to forecast these kinds of behaviors to achieve the calculated peak-cut and avoid another new peak-load in the evening.
  • In case of the generated electricity from RE including wind and PV increases, the additional capacity of EVs and used EV batteries is required to buffer the fluctuating electricity generated from RE.

6. Conclusions

The extended utilization of EVs and their used batteries to support electricity on a small-scale EMS has been proposed and demonstrated. Theoretically, this utilization is feasible, and it is largely expected that it will improve generally the economic performance of EVs. From the experimental study, it was proved that load leveling through peak-shift and peak-cut can be achieved by setting the peak-cut threshold and controlling both charging and discharging behaviors of EVs and used EV batteries. Hence, the total load during peak hours can be reduced leading to lower total electricity costs. In this load leveling, forecasting of load and resources including electricity from EVs and RE generation becomes a very important task to achieve a successful load leveling.
Some further challenges related to utilization of EVs and used EV batteries in supporting certain EMS relates strongly to some issues including supply, demand and EV availability forecast. Supply forecast includes available RE generation, electricity price on the market, and possible electricity generation with lower costs. In addition, the accuracy of demand forecasts including weather and human behavior is also one important key to success as it deals strongly with the air conditioning demand which actually becomes the largest part of fluctuating load.

Acknowledgments

This research was financially supported in part by Mitsubishi Motors Corporation, Japan. The demonstration test bed used in this study was implemented as the collaborative project among Mitsubishi Corporation, Mitsubishi Motors Corporation, and Mitsubishi Electric Corporation.

Author Contributions

Muhammad Aziz and Takuya Oda contributed to the overall study and analysis. In addition, Muhammad Aziz wrote the manuscript with a support from Takashi Mitani and Yoko Watanabe, especially in data analysis. Takao Kashiwagi read, revised and approved the manuscript.

Abbreviations

BEMSbuilding energy management system
CEMScommunity energy management system
EMSenergy management system
EVelectric vehicle
FEMSfactory energy management system
HEMShouse energy management system
PCSpower conditioning system
PVphotovoltaic
RErenewable energy
SOCstate of charge
V2Gvehicle to grid
VISvehicle information system

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Kley, F.; Lerch, C.; Dallinger, D. New business models for electric cars—A holistic approach. Energy Policy 2011, 39, 3392–3403. [Google Scholar] [CrossRef]
  2. Barkenbus, J.N. Our electric automotive future: CO2 savings through a disruptive technology. Policy Soc. 2009, 27, 399–410. [Google Scholar] [CrossRef]
  3. Thiel, C.; Perujo, A.; Mercier, A. Cost and CO2 aspects of future vehicle options in Europe under new energy policy scenarios. Energy Policy 2010, 38, 7142–7151. [Google Scholar] [CrossRef]
  4. Kempton, W.; Letendre, S.E. Electric vehicles as a new power source for electric utilities. Transp. Res. D 1997, 2, 157–175. [Google Scholar] [CrossRef]
  5. Kempton, W.; Kubo, T. Electric-drive vehicles for peak power in Japan. Energy Policy 2000, 28, 9–18. [Google Scholar] [CrossRef]
  6. Tomic, J.; Kempton, W. Using Fleets of electric-drive vehicles for grid support. J. Power Sources 2007, 168, 459–468. [Google Scholar] [CrossRef]
  7. White, C.D.; Zhang, K.M. Using vehicle-to-grid technology for frequency regulation and peak-load reduction. J. Power Sources 2011, 196, 3972–3980. [Google Scholar] [CrossRef]
  8. Aziz, M.; Oda, T.; Morihara, A.; Murakami, T.; Momose, N. Utilization of EVs and their used batteries in factory load leveling. In Proceedings of the 2014 IEEE PES Innovative Smart Grid Technologies Conference (ISGT), Washington, DC, USA, 19–22 February 2014.
  9. Aziz, M.; Oda, T.; Kashiwagi, T. Extended utilization of electric vehicles and their re-used batteries to support the building energy management system. In Energy Procedia, Proceedings of the 7th International Conference on Applied Energy-ICAE2015, Abu Dhabi, UAE, 28–31 March 2015.
  10. Drude, L.; Pereira, L.P.; Ruther, R. Photovoltaics (PV) and electric vehicle-to-grid (V2G) strategies for peak demand reduction in urban regions in Brail in a smart grid environment. Renew. Energy 2014, 68, 443–451. [Google Scholar] [CrossRef]
  11. Kempton, W.; Tomic, J. Vehicle-to-grid power fundamentals: Calculating capacity and net revenue. J. Power Sources 2005, 144, 268–279. [Google Scholar] [CrossRef]
  12. Gao, B.; Zhang, W.; Tang, Y.; Hu, M.; Zhu, M.; Zhan, H. Game-theoretic energy management for residential users with dischargeable plug-in electric vehicles. Energies 2014, 7, 7499–7518. [Google Scholar] [CrossRef]
  13. Takagi, M.; Yamamoto, H.; Yamaji, K. Analysis of expanded allowable capacity of wind power in power grid by charge control for plug-in hybrid electric vehicles. In Proceedings of the 28th USAEE/IAEE North American Conference, New Orleans, LA, USA, 3–5 December 2008; pp. 1–15.
  14. Galus, M.D.; la Fauci, R.; Andersson, G. Investigating PHEV wind balancing capabilities using heuristics and model predictive control. In Proceedings of the IEEE Power and Energy Society (PES) General Meeting, Minneapolis, MN, USA, 25–29 July 2010; pp. 1–8.
  15. Han, S.; Han, S. Economic feasibility of V2G frequency regulation in consideration of battery wear. Energies 2013, 6, 748–765. [Google Scholar] [CrossRef]
  16. Viswanathan, V.V.; Kintner-Meyer, M. Second use of transportation batteries: Maximizing the value of batteries for transportation and grid services. IEEE Trans. Veh. Technol. 2011, 60, 2963–2970. [Google Scholar] [CrossRef]
  17. Williams, B.D.; Lipman, T.E. Strategies for transportation electric fuel implementation in California: Overcoming battery first-cost hurdles. In PIER Final Project Report; University of California: Berkeley, CA, USA, 2010; CEC-500-2009-091. [Google Scholar]
  18. Cready, E.; Lippert, J.; Pihl, J.; Weinstock, I.; Symons, P.; Jungst, R.G. Technical and economic feasibility of applying used EV batteries in stationary applications. In DOE Energy Storage Systems Program; Sandia National Laboratories: Albuquerque, NM, USA, 2003; SAND2002-4084. [Google Scholar]
  19. Alimisis, V.; Hatziargyriou, N.D. Evaluation of a hybrid power plant comprising used EV-batteries to complement wind power. IEEE Trans. Sustain. Energy 2013, 4, 286–293. [Google Scholar] [CrossRef]
  20. Neubauer, J.; Pesaran, A.; Howell, D. Secondary use of EV and PHEV batteries—Opportunities and challenges. In Proceedings of the 10th Advanced Automotive Battery Conference, Orlando, FL, USA, 19–21 May 2010. NREL/PR-540-48872.
  21. Berardino, J.; Nwankpa, C. Statistics of building-specific load forecasting models. In Proceedings of the North American Power Symposium (NAPS), Manhattan, KS, USA, 22–24 September 2013; pp. 1–6.
  22. Vetter, J.; Novak, P.; Wagner, M.R.; Veit, C.; Moller, K.C.; Besenhard, J.O.; Winter, M.; Wohlfahrt-Mehrensc, M.; Voglerc, C.; Hammouched, A.; et al. Ageing mechanism in lithium-ion batteries. J. Power Sources 2005, 147, 269–281. [Google Scholar] [CrossRef]
  23. Peterson, S.B.; Apt, J.; Whitacre, J.F. Lithium-ion battery cell degradation resulting from realistic vehicle and vehicle-to-grid utilization. J. Power Sources 2010, 195, 2385–2392. [Google Scholar] [CrossRef]
  24. Marongiu, A.; Roscher, M.; Sauer, D.U. Influence of the vehicle-to-grid strategy on the aging behavior of lithium battery electric vehicles. Appl. Energy 2015, 137, 899–912. [Google Scholar] [CrossRef]

Share and Cite

MDPI and ACS Style

Aziz, M.; Oda, T.; Mitani, T.; Watanabe, Y.; Kashiwagi, T. Utilization of Electric Vehicles and Their Used Batteries for Peak-Load Shifting. Energies 2015, 8, 3720-3738. https://0-doi-org.brum.beds.ac.uk/10.3390/en8053720

AMA Style

Aziz M, Oda T, Mitani T, Watanabe Y, Kashiwagi T. Utilization of Electric Vehicles and Their Used Batteries for Peak-Load Shifting. Energies. 2015; 8(5):3720-3738. https://0-doi-org.brum.beds.ac.uk/10.3390/en8053720

Chicago/Turabian Style

Aziz, Muhammad, Takuya Oda, Takashi Mitani, Yoko Watanabe, and Takao Kashiwagi. 2015. "Utilization of Electric Vehicles and Their Used Batteries for Peak-Load Shifting" Energies 8, no. 5: 3720-3738. https://0-doi-org.brum.beds.ac.uk/10.3390/en8053720

Article Metrics

Back to TopTop