Next Article in Journal
The Effects of Earthquake Experience on Disaster Education for Children and Teens
Previous Article in Journal
The Influence of Role Models on the Sedentary Behaviour Patterns of Primary School-Aged Children and Associations with Psychosocial Aspects of Health
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Occupational ALARA Planning for Reactor Pressure Vessel Dismantling at Kori Unit 1

Department of NPP Engineering, KEPCO International Nuclear Graduate School, 658-91 Haemaji-ro, Seosaeng-myeon, Ulju-gun, Ulsan 45014, Korea
*
Author to whom correspondence should be addressed.
Int. J. Environ. Res. Public Health 2020, 17(15), 5346; https://0-doi-org.brum.beds.ac.uk/10.3390/ijerph17155346
Submission received: 22 June 2020 / Revised: 15 July 2020 / Accepted: 22 July 2020 / Published: 24 July 2020
(This article belongs to the Section Occupational Safety and Health)

Abstract

:
Assessing workers’ safety and health during the decommissioning of nuclear power plants (NPPs) is an important procedure in terms of occupational radiation exposure (ORE). Optimizing the radiation exposure through the “As Low As Reasonably Achievable (ALARA)” principle is a very important procedure in the phase of nuclear decommissioning. Using the VISIPLAN 3D ALARA planning tool, this study aimed at assessing the radiological doses to workers during the dismantling of the reactor pressure vessel (RPV) at Kori NPP unit 1. Fragmentation and segmentation cutting processes were applied to cut the primary component. Using a simulation function in VISIPLAN, the external exposure doses were calculated for each work operation. Fragmentation involved 18 operations, whereas segmentation comprised 32 operations for each fragment. Six operations were additionally performed for both hot and cold legs of the RPV. The operations were conducted based on the radioactive waste drum’s dimensions. The results in this study indicated that the collective doses decreased as the components were cut into smaller segments. The fragmentation process showed a relatively higher collective dose compared to the segmentation operation. The active part of the RPV significantly contributed to the exposure dose and thus the shielding of workers and reduced working hours need to be considered. It was found that 60Co contained in the stainless steel of the reactor vessel greatly contributed to the dose as an activation material. The sensitivity analysis, which was conducted for different cutting methods, showed that laser cutting took a much longer time than plasma cutting and contributed higher doses to the workers. This study will be helpful in carrying out the occupational safety and health management of decommissioning workers at Kori NPP unit 1 in the near future.

1. Introduction

Kori unit 1, a two-loop Westinghouse pressurized light water reactor with an output of 587 MWe, was the first Korean commercial nuclear power plant (NPP) and started its operation in April, 1978 and was permanently shut down for decommissioning in June, 2017. The national strategy for the decommissioning of Kori unit 1 was an immediate decommissioning (DECOM) and the end state of the NPP site was determined as brownfield land, where the site release criterion would be 0.1 mSv/yr. The nuclear decommissioning of Kori unit 1 was scheduled to last for at least 15 years; the cooling of spent nuclear fuel in 2017–2022, decontamination and dismantling in 2022–2028, and site restoration by 2032 [1,2]. During the decommissioning phase, several activities, including the preparation of a final decommissioning plan (FDP) which should be submitted to the regulator within 5 years after permanent shutdown, i.e., by June, 2022, public hearings with residents near Kori NPP unit 1 for 1 year, the completion of spent nuclear fuel transfer by 2025, the decontamination and dismantling of structures, systems and components (SSCs) of Kori unit 1, the treatment and conditioning of radioactive wastes and the storage and the final disposal of radioactive wastes, have to be undertaken with proper steps in order to achieve the desired end state within the planned time schedule. However, the activities of the dismantling and segmentation of the activated reactor pressure vessel (RPV), RPV internals and contaminated steam generators and pressurizers pose a serious radiation exposure risk to the decommissioning workers. One of the most challenging tasks during the decommissioning of Kori unit 1 was considered to be the removal of highly radioactive internal components of the RPV [3]. Boric acid was used in Kori unit 1 coolant and hence the use of stainless steel was required for the protection of reactor internals inside of a carbon steel reactor vessel. Cobalt and other metals, such as nickel, were some of the impurities used in the stainless steel and were ultimately activated and contributed to high radionuclide concentrations in the RPV and RPV internals. Ample knowledge of the “As Low as Reasonably Achievable” (ALARA) principle of radiation protection is inevitable to optimize the exposure of radiation workers. ALARA means making every reasonable effort to keep the exposure of radiation workers as far below the limits as possible, consistent with the purpose for which the license activity was undertaken in relation to benefits to the workers’ health and safety, and other socio-economic considerations. Dose planning and estimation were considered as vital phases of the ALARA principle implementation, thus the selection of proper technologies of dismantling equipment that allow for reducing the personnel’s collective dose was highly recommended. The three principles used in ALARA for reducing external exposure are time, distance and shielding. Various types of software that take into account the occupational radiation exposure have been developed to plan the dismantling activities [4,5,6]. In this paper, the modeling results of radiation doses to workers during the dismantling of a reactor pressure vessel at Kori unit 1 was conducted using VISIPLAN computer code [7,8]. The computer code “VISIPLAN 3D ALARA planning tool”, developed by the SCK-CEN Laboratory in Belgium, has been widely used to solve radiation protection problems resulting from exposure to direct radiation, such as the handling of fiber-reinforced concrete containers with conditioned radioactive waste [9,10,11,12,13].

2. Materials and Methods

The VISIPLAN 3D ALARA planning tool is a new calculation tool developed to facilitate the planning of the work based on 3D geometrical, material and radiological information. The software considers dose assessments for external exposure to gamma radiation. The dose calculations are based on a point-kernel method with a build-up correction, whereby each small source is called a kernel, and the process of integration, where the contribution to the dose of each point is added up, is called “point kernel” integration. The VISIPLAN methodology consists of four steps: model building, general analysis, detailed planning and follow-up, as shown in Figure 1.
The model building stage, which is the first step in the analysis, is the characterization of the site or work area. The geometrical and material information required can be derived from technical drawings or survey techniques. Once the model is defined, the general analysis stage follows and involves the calculation of dose maps of the working areas. The dose rates can be displayed as contours or colorful patterns on grids perpendicular to the x, y and z axes of the model. The tools available for the detailed planning phase involve a trajectory calculation and a scenario building tool. The trajectory contains information involving the task description, the location and the duration of the sequential tasks to be performed. The graphs and task lists produced in the detailed planning stage make it possible to perform a thorough follow up of the dose account during the work. This is achieved through comparisons of the predicted and the received radiation doses. The VISIPLAN code only considers the transport of radiation through intervening shielding in the line of sight path from the source to the dose point. The photon fluence rate at a dose point originating from a volume source is determined by considering the volume source as consisting of a number of point sources. The photon fluence rate can be found by adding the contribution of every point source to the dose at the dose point. The photon fluency rate Φ (cm−2s−1) can be expressed as:
ϕ = v S . B . e x 4 π . ρ 2 d V
where S is the source strength representing the number of photons emitted by the source per unit volume and per unit time, B is the build-up factor, x represents the main free paths and ρ is the distance from a point source. This method is called “point kernel” integration. The volume integration scheme used in VISIPLAN is based on a Monte Carlo sampling of source positions in the source volume. The number of sampling points (Ns) can be chosen by the user. The point kernel equation above changes to the following form:
ϕ = i = 1 N s S t o t N S   B . e x i 4. π . ρ i 2
where xi and ρi are the mean free paths and the distance (cm) from the i-th sampling point, respectively. The equations above consider a monoenergetic photon source of source strength Stot. The sources encountered in many shielding problems emit photons at different energies. The VISIPLAN 3D ALARA planning tool uses, at present, a formulation where 25 energy bins are used. A source spectrum derived from other calculation codes needs to be re-grouped to the 25 energy group format when it is used in calculations with VISIPLAN. The photon fluence rate at the dose point in the energy group Eb is calculated as:
ϕ E b = i = 1 N x S t o t . F E b N s B E b 4. π . ρ i 2
where FEb is the number of photons emitted in the energy group Eb per total activity Stot of the source. The dose rate at the dose point is determined by using:
D o s e   r a t e = b = 1 25 h E b . ϕ E b
where hEb is the dose conversion factor for energy Eb. The dose rates in the VISIPLAN results are expressed in mSv.h−1. Input parameters, such as material, outer radius and length, were acquired from the designing parameters of Kori unit 1. The source terms used to perform the calculations during the decommissioning of the Kori unit-1 RPV are shown in Table 1 [14]. According to recent studies, the most significant radionuclide that contributed to worker doses in nuclear power plants is 60Co, which was responsible for over 80% of out-of-core radiation fields.
Three working groups were considered for each of the three parts of the RPV. Each group had six cutters to carry out the operation of the fragmentation and segmentation of the RPV and one radiation protection officer (RPO) responsible for the safety of the cutters. The cutter was assumed to perform the cutting activities within the range of 30–38 cm, whereas the RPO was assumed to be located at a distance of 100–130 cm from the component. Four main commercial cutting technologies for decommissioning were introduced, i.e., waterjet cutting, laser cutting, shear cutting and plasma cutting technologies, as shown in Table 2. Waterjet cutting technology uses high pressure water for abrasive injection, whereas shear cutting uses two blades to cut an object on the same principle as a pair of scissors. Plasma cutting, which was selected as the best cutting technology for the reactor vessel in this study, uses a direct current arc to cause a metal oxidation reaction.

3. Results and Discussion

The RPV, with a total height of 14.67 m, was divided into two separate parts, consisting of a cylindrical body and a spherical cap, as shown in Figure 2. The inside diameter of the RPV and the shell thickness was 4.17 m and 0.26 m, respectively, giving it a total diameter of 4.7 m. Based on the waste drum’s specification, the cylindrical body, with a length of 12.4 m, was first divided into 18 pieces using the fragmentation process and then each of the 18 pieces was cut to 32 segments. The spherical cap part, with a total length of 2.27 m, was divided into four pieces. The top two fragments were cut into 32 segments, while the remaining two smaller fragments were cut into 10 segments. In addition, six fragmentation operations were performed for the cold and hot legs, with a height of 0.68 m for each fragment, as shown in Figure 3. The total number of pieces for the whole cutting process was 664 pieces. This procedure for cutting the RPV was based on the dimensions of the waste drum, with a height and diameter of 0.8 m and 0.57 m, respectively.
The cutting time for each axial part of the cylindrical body of the RPV was calculated as follows:
Circumference of RPV = L = 2 π r = 2 × 3.14 × 2.35 = 14.76 m
Time = 14760   mm 15   m m / m i n = 984   min
The cutting time for each axial part of the spherical cap of the RPV was calculated as follows:
Top two fragments’ circumference of the spherical cap of the RPV = 2 × 3.14 ×1.175 = 7.4 m
Time = 7400   mm 15   m m / m i n = 493   min
The two smaller fragments’ circumference of the spherical cap of the RPV = 2 × 3.14 × 0.587 = 3.69 m
Time = 3690   mm 15   m m / m i n = 246   min
The cutting time for each radial part of the RPV was calculated as follows:
Height of fragment = 0.68 m × 32 = 21.08 m
Time = 21080   mm 15   m m / m i n = 1405   min
The total time and dose prognoses for the fragmentation operation of the upper part of the RPV are presented in Table 3. Six cutters (1–6) were considered for the upper part fragmentation. The total time and accumulated dose for the cutting of each fragment per worker are shown in Table 4. The total work time taken for the RPO was 1896 minutes and the total accumulated dose was 1.0 × 102 mSv.
Cutters 7~12 were considered for one cutting of the active part of the RPV using the fragmentation process. For six active parts, the total time and accumulated dose are shown in Table 5. In Table 6, the total time and accumulated dose for the cutting of each fragment per worker are presented. For the radiation protection officer, the total work time taken was 948 min and the total accumulated dose was 2.8 × 103 mSv.
Cutters 13–18 were considered for the operation of cutting the lower part. Table 7 shows the total time and accumulated dose for one cutting of the lower part of the RPV, whereas Table 8 shows the total time and accumulated dose for one cutting of each fragmentation per worker. The total work time for the radiation protection officer was 948 mins and the total accumulated dose was 1.10 × 102 mSv.
Using the segmentation process, cutters 1–6 were considered for cutting the upper part of the RPV. The total time and accumulated dose for the cutting of one segment of the upper part of the RPV is shown in Table 9. Table 10 presents the total time and accumulated dose for the cutting of each segment per worker. The total work time and total accumulated dose received by the the radiation protection officer was 1405 min and 1.60 × 102 mSv, respectively.
Cutters 7–12 were considered for the RPV active part segmentation. Table 11 shows the total time and accumulated dose for one segmentation process of the active part of the RPV. Table 12 shows the total time and accumulated dose for the cutting of each segment per worker. For the RPO, the total work time taken was 1405 min and the total accumulated dose was 1.00 × 103 mSv.
Table 13 presents the total time and accumulated dose for each segmentation process of the RPV for cutters 13–18. Table 14 presents the total time and accumulated dose for the cutting of each segment per worker. The time taken and total accumulated dose received by the radiation protection officer was 1405 minutes and 9.50 × 101 mSv, respectively.
Table 15 presents the collective time and dose to the decommissioning workers for both the fragmentation and segmentation operations. The total time duration, dose rate, task dose and accumulated dose are shown for the different cutter tasks. For the fragmentation process, the collective dose for the upper part, active part and lower part were 6.0 × 102, 1.7 × 104 and 9.1 × 102 man-mSv, respectively. For the segmentation process, the collective dose for the upper part, active part and lower part were 5.7 × 102, 6.2 × 103 and 9.5 × 102 man-mSv, respectively. The fragmentation of the active part contributed a higher dose compared to the other parts. The most significant radionuclide that contributed to the workers’ doses at Kori unit 1 was 60Co, which was responsible for over 80% of out-of-core radiation fields. Although 55Fe had the highest activities, the 60Co energy level was higher, hence the reason for its contribution. The time that was simulated for the fragmentation process of the upper, active and lower parts was 23.7 man-days, 23.7 man-days and 31.6 man-days, respectively. The time that was taken to cut the upper, active and lower parts using the segmentation process was 35.12 man-days, 35.12 man-days and 46.8 man-days, respectively. Segmentation operations took a longer time compared to the fragmentation process. Lastly, the total time that was taken to finish the fragmentation and segmentation processes of cutting the RPV of Kori unit 1 was 196 man-days.
Sensitivity analysis was performed for the cutting technologies of laser and plasma for both the fragmentation and segmentation operations. The speed of plasma cutting was considered higher, at 15 mm/min, compared to 100 mm/min for the laser cutting, hence it took a longer time and led to a larger dose value received by the workers. The overall scenarios for laser cutting and plasma cutting are shown in Figure 4 and Figure 5. The occupational exposure of any worker should be controlled in order not to exceed the dose limits of 20 mSv per year averaged over five consecutive years, as recommended by the International Commission on Radiological Protection (ICRP). The values predicted in this study were relatively higher since we focused on the RPV, which was a primary component of the NPP, and thus strict measures, such as reduced time and increased shielding should be taken to protect decommissioning workers and keep the radiation exposure to the workers as low as possible.

4. Conclusions

We performed the preliminary estimation of occupational exposure for radiation workers using the VISIPLAN 3D ALARA planning tool during the decommissioning phase of a reactor pressure vessel at Kori NPP unit 1, which will be scheduled in 2022–2028. Different cutting methods and cutting processes of fragmentation and segmentation of the reactor pressure vessel of Kori unit 1 were simulated in order to optimize the working time and exposure dose of radiation workers through quantitative risk modeling. It was found that VISIPLAN would be a good tool to plan and manage the occupational safety and health of radiation workers for the decommissioning of Kori NPP unit 1 in the near future.

Author Contributions

Conceptualization, J.K. and B.T.; methodology, J.K. and B.T; software, B.T.; validation, J.K. and B.T; formal analysis, B.T.; investigation, J.K. and B.T; resources, J.K. and B.T; data curation, B.T.; writing—original draft preparation, B.T.; writing—review and editing, J.K.; visualization, B.T.; supervision, J.K.; project administration, J.K.; funding acquisition, J.K. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by the 2020 Research Fund of the KEPCO International Nuclear Graduate School (KINGS), the Republic of Korea. This research was also supported by the National Research Foundation of Korea (NRF) grant funded by the Korea government (Ministry of Science and ICT) (No. NRF-2020M2A8A4022526).

Acknowledgments

Special acknowledgment goes to the Belgian Nuclear Research Centre, SCK∙CEN, for the academic license of VISIPLAN software.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Nuclear Power Operation of KHNP. Available online: http://www.khnp.co.kr/eng/content/529/main.do?mnCd=EN03020101/ (accessed on 12 November 2019).
  2. Sung, N.-W. Worker Exposure Dose Evaluation of the Steam Generator Decommissioning Process in the Kori-1. Master’s Thesis, Graduate School of Ulsan National Institute of Science and Technology, Ulsan, Korea, 2018. [Google Scholar]
  3. Lee, B.-S. Optimization of reactor pressure vessel internals segmentation in Kore. Atw: Int. J. Nucl. Power. 2017, 62, 6546–6558. [Google Scholar]
  4. Audrius, S.; Poskas, P.; Gintautas, P.; Grigaliuniene, D. Modeling of the radiation doses during dismantling of rbmk-1500 reactor emergency core cooling system large diameter pipes. Ann. Nucl. Energy 2015, 85, 159–165. [Google Scholar]
  5. Joseph, B.; Segerud, P.; Sanchez, M. Best practices for preparing vessel internals segmentation projects. In Proceedings of the International Symposium on Preparation for Decommissioning-PREDEC 2016, Lyon, France, 16–18 February 2016. [Google Scholar]
  6. Choi, Y.; Lee, S.; Kim, C. Evaluation on radioactive waste disposal amount of kori unit 1 reactor vessel considering cutting and packaging methods. Nucl. Fuel Cycle Waste Technol. 2016, 14, 1231–1234. [Google Scholar] [CrossRef]
  7. SCK-CEN. VISIPLAN Description. Available online: https://www.visiplan.be/en/ALARA (accessed on 12 November 2019).
  8. Vermeersch, F. VISIPLAN 3D ALARA Planning Tool, Version 4.0; Step by Step Guide, SCK∙CEN, Boeretang 200, B-2400 Mol, Belgium. 2016. Available online: https://www.visiplan.be/-/media/Files/Visiplan/Marketing/visiplan_leaflet.pdf (accessed on 12 November 2019).
  9. Vermeersch, F. Alara pre-job studies using the visiplan 3D alara planning tool. Radiat. Prot. Dosim. 2005, 115, 2942–2997. [Google Scholar] [CrossRef] [PubMed]
  10. Peter, T.; Necas, V. Conditional release of materials from decommissioning process into the environment in the form of steel railway tracks. Nucl. Eng. Des. 2009, 239, 1155–1161. [Google Scholar]
  11. Maggini, A.; Ciolini, R.; Pistelli, S.; Garneri, E. Strategies and dismantling solutions for RPV internals of trino npp. Prog. Nucl. Energy 2016, 93, 67–75. [Google Scholar] [CrossRef]
  12. David, B.; Martin, L.; Andrej, S.; Vladimir, N. Comparison of deterministic and stochastic methods for external gamma dose rate calculation in the decommissioning of nuclear power plants. Ann. Nucl. Energy 2019, 134, 67–76. [Google Scholar]
  13. Perez, J.M.; Vermeersch, F.; Vela, O.; Burgos, E.d. Radiometric modeling through the combined use of the EDR gamma scanner and the visiplan dose assessment tool. Nucl. Instrum. Methods Phys. Res. A 2004, 533, 5715–5783. [Google Scholar] [CrossRef]
  14. Hwang, Y.-H.; Hwang, S.-J.; Yoon, J.-Y. Study on radiological inventory assessment of kori 1 reactor vessel. In Proceedings of the Korean Radioactive Waste Society Conference, Jeju, Korea, 30 October–1 November 2019; pp. 205–206. [Google Scholar]
Figure 1. The main stages in the methodology of VISIPLAN.
Figure 1. The main stages in the methodology of VISIPLAN.
Ijerph 17 05346 g001
Figure 2. Illustration of the reactor pressure vessel at Kori unit 1.
Figure 2. Illustration of the reactor pressure vessel at Kori unit 1.
Ijerph 17 05346 g002
Figure 3. Description of reactor pressure vessel (RPV) and cylindrical cutting method.
Figure 3. Description of reactor pressure vessel (RPV) and cylindrical cutting method.
Ijerph 17 05346 g003
Figure 4. Comparison between laser cutting and plasma cutting for the fragmentation process.
Figure 4. Comparison between laser cutting and plasma cutting for the fragmentation process.
Ijerph 17 05346 g004
Figure 5. Comparison between laser cutting and plasma cutting for the segmentation process.
Figure 5. Comparison between laser cutting and plasma cutting for the segmentation process.
Ijerph 17 05346 g005
Table 1. Source terms in different parts of reactor pressure vessel.
Table 1. Source terms in different parts of reactor pressure vessel.
SerialNuclideActive Part (Bq)Upper Part (Bq)Lower Part (Bq)Half-Life
155Fe6.96 × 10141.28 × 10133.56 × 1092.74 years
260Co2.23 × 10123.52 × 10105.25 × 1065.27 years
3152Eu6.62 × 1091.75 × 1081.56 × 10413.52 years
4154Eu1.23 × 1092.35 × 1071.65 × 1038.59 years
5134Cs2.60 × 1084.69 × 1069.08 × 1022.06 years
6155Eu3.76 × 1073.16 × 1051.50 × 1014.76 years
7110mAg3.28 × 1053.75 × 1033.43 × 100250 days
899Tc2.35 × 1043.96 × 1021.43 × 10−26 hours
Total Activity6.98 × 10141.28 × 10133.59 × 109
Table 2. Thickness and speed of main cutting technologies.
Table 2. Thickness and speed of main cutting technologies.
Water Jet CuttingLaser CuttingShear CuttingPlasma Cutting
Thickness~20 cm~20 cm~20 cm~20 cm
Speed70–100 mm/min15–45 mm/min15–50 mm/min150 mm/min
Table 3. Work time and estimated dose for the fragmentation of the upper part.
Table 3. Work time and estimated dose for the fragmentation of the upper part.
Total work time (min)1896.0Accumulated dose (mSv)1.0 × 102
Max. work time (min)1968.1Max. accumulated dose (mSv)1.1 × 102
Min. work time1823.9Min. accumulated dose (mSv)9.4 × 101
Table 4. Task information for the fragmentation of the upper part.
Table 4. Task information for the fragmentation of the upper part.
Task No.Task DescriptionDuration (min)Dose Rate (mSv/h)Task Dose (mSv)Accumulative Dose (mSv)
1Cutter 11351.30 × 1012.90 × 1012.90 × 101
2Cutter 21658.30 × 10−42.30 × 10−32.90 × 101
3Cutter 31297.50 × 1001.60 × 1014.50 × 101
4Cutter 41727.00 × 1002.00 × 1016.50 × 101
5Cutter 51657.60 × 10−42.10 × 10−36.50 × 101
6Cutter 61821.10 × 1013.40 × 1011.00 × 102
7RPO 19488.80 × 10−41.40 × 10−21.00 × 102
Table 5. Work time and estimated dose for the fragmentation of the active part.
Table 5. Work time and estimated dose for the fragmentation of the active part.
Total work time (min)1896.0Accumulated dose (mSv)2.8 × 103
Max. work time (min)1971.0Max. accumulated dose (mSv)3.0 × 103
Min. work time1821.0Min. accumulated dose (mSv)2.6 × 103
Table 6. Task information for the fragmentation of the active part.
Table 6. Task information for the fragmentation of the active part.
Task No.Task DescriptionDuration (min)Dose Rate (mSv/h)Task Dose (mSv)Acc. Dose (mSv)
1Cutter_71655.70 ×1021.60 × 1031.60 × 103
2Cutter_81723.10 × 1018.80 × 1011.60 × 103
3Cutter_91822.10 × 1016.50 × 1011.70 × 103
4Cutter_101653.20 × 1028.70 × 1022.60 × 103
5Cutter_111291.90 × 1014.10 × 1012.60 × 103
6Cutter_121358.10 × 1011.80 × 1022.80 × 103
7RPO 29482.60 × 10−24.10 × 10−12.80 × 103
Table 7. Work time and estimated dose for the fragmentation of the lower part.
Table 7. Work time and estimated dose for the fragmentation of the lower part.
Total work time (min)1896.0Accumulated dose (mSv)1.1 × 102
Max. work time (min)1964.5Max. accumulated dose (mSv)1.2 × 102
Min. work time1827.5Min. accumulated dose (mSv)1.1 × 102
Table 8. Task information for the fragmentation of the lower part.
Table 8. Task information for the fragmentation of the lower part.
Task No.Task DescriptionDuration (min)Dose Rate (mSv/h)Task Dose (mSv)Acc. Dose (mSv)
1Cutter_131291.20 × 1012.70 × 1012.70 × 101
2Cutter_141651.20 × 10−23.30 × 10−22.70 × 101
3Cutter_151357.80 × 1001.80 × 1014.40 × 101
4Cutter_161829.30 × 1002.80 × 1017.20 × 101
5Cutter_171657.00 × 10−31.90 × 10−27.20 × 101
6Cutter_181721.40 × 1014.10 × 1011.10 × 102
7RPO_39481.30 × 10−22.10 × 10−11.10 × 102
Table 9. Work time and estimated dose for the segmentation of the upper part.
Table 9. Work time and estimated dose for the segmentation of the upper part.
Time and Dose Prognoses
Total work time (min)2810.0Accumulated dose (mSv)1.6 × 102
Max. work time (min)2826.3Max. accumulated dose (mSv)1.6 × 102
Min. work time2793.9Min. accumulated dose (mSv)1.6 × 101
Table 10. Task information for the segmentation of upper part.
Table 10. Task information for the segmentation of upper part.
Task No.Task DescriptionDuration (min)Dose Rate (mSv/h)Task Dose (mSv)Acc. Dose (mSv)
1cutter_12203.80 × 1001.40 × 1011.40 × 101
2cutter_23004.20 × 1002.10 × 1013.50 ×101
3cutter_32608.90 × 1003.90 × 1017.30 × 101
4cutter_42008.40 × 1002.80 × 1011.00 × 102
5cutter_51854.40 × 1001.30 × 1011.10 × 102
6cutter_62402.70 × 1001.10 × 1011.30 × 102
7RPO14051.40 × 1003.30 × 1011.60 × 102
Table 11. Work time and estimated dose for the segmentation of the active part.
Table 11. Work time and estimated dose for the segmentation of the active part.
Total work time (min)2810.0Accumulated dose (mSv)1.0 × 103
Max. work time (min)2836.8Max. accumulated dose (mSv)1.0 × 103
Min. work time2783.2Min. accumulated dose (mSv)1.0 × 103
Table 12. Task information for the segmentation of the active part.
Table 12. Task information for the segmentation of the active part.
Task No.Task DescriptionDuration (min)Dose Rate (mSv/h)Task Dose (mSv)Acc. Dose (mSv)
1cutter_12603.60 × 1011.60 × 1021.60 × 102
2cutter_22003.50 × 1011.20 × 1022.70 × 102
3cutter_32202.70 × 1019.90 × 1013.70 × 102
4cutter_41854.10 × 1011.30 × 1025.00 × 102
5cutter_53003.60 × 1011.80 × 1026.80 × 102
6cutter_62403.60 × 1011.40 × 1028.30 × 102
7RPO 114059.20 × 1002.10 × 1021.00 × 103
Table 13. Work time and estimated dose for the segmentation of the lower part.
Table 13. Work time and estimated dose for the segmentation of the lower part.
Total work time (min)2810.0Accumulated dose (mSv)9.5 × 101
Max. work time (min)2838.0Max. accumulated dose (mSv)9.6 × 101
Min. work time2782.0Min. accumulated dose (mSv)9.4 × 101
Table 14. Task information for the segmentation of the lower part.
Table 14. Task information for the segmentation of the lower part.
Task No.Task DescriptionDuration (min)Dose Rate (mSv/h)Task Dose (mSv)Acc. Dose (mSv)
1Cutter_11854.20 × 1001.30 × 1011.30 × 101
2Cutter_22608.00 × 1003.40 × 1014.70 × 101
3Cutter_32204.00 × 1001.50 × 1016.20 × 101
4Cutter_42002.10 × 1006.90 × 1006.90 × 101
5Cutter_52401.50 × 1006.20 × 1007.50 × 101
6Cutter_63001.40 × 1006.80 × 1008.20 × 101
7RPO14055.60 x 10−11.30 x 1019.50 x 101
Table 15. Collective time and dose of fragmentation and segmentation processes.
Table 15. Collective time and dose of fragmentation and segmentation processes.
ScenarioCollective Time (man-h)Collective Dose (man-mSv)
Upper part fragmentation189.606.0 × 102
Active part fragmentation189.601.7 × 104
Lower part fragmentation252.809.1 × 102
ScenarioCollective Time (man-h)Collective Dose (man-mSv)
Upper part segmentation281.005.7 × 102
Active part segmentation281.006.2 × 103
Lower part segmentation374.609.5 × 102
Total 1568.6 man-h = 196 man-days

Share and Cite

MDPI and ACS Style

Kim, J.; Tseren, B. Occupational ALARA Planning for Reactor Pressure Vessel Dismantling at Kori Unit 1. Int. J. Environ. Res. Public Health 2020, 17, 5346. https://0-doi-org.brum.beds.ac.uk/10.3390/ijerph17155346

AMA Style

Kim J, Tseren B. Occupational ALARA Planning for Reactor Pressure Vessel Dismantling at Kori Unit 1. International Journal of Environmental Research and Public Health. 2020; 17(15):5346. https://0-doi-org.brum.beds.ac.uk/10.3390/ijerph17155346

Chicago/Turabian Style

Kim, Juyoul, and Batbuyan Tseren. 2020. "Occupational ALARA Planning for Reactor Pressure Vessel Dismantling at Kori Unit 1" International Journal of Environmental Research and Public Health 17, no. 15: 5346. https://0-doi-org.brum.beds.ac.uk/10.3390/ijerph17155346

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop