Next Article in Journal
Consequences of Deep Rolling at Elevated Temperature on Near-Surface and Fatigue Properties of High-Manganese TWIP Steel X40MnCrAl19-2
Next Article in Special Issue
Method of Planning Repairs of the Installation including Building Waste
Previous Article in Journal
Efficient Moment-Independent Sensitivity Analysis of Uncertainties in Seismic Demand of Bridges Based on a Novel Four-Point-Estimate Method
Previous Article in Special Issue
Effects of Recycled Fine Glass Aggregates on Alkali Silica Reaction and Thermo-Mechanical Behavior of Modified Concrete
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Economic Impact Analysis of the Application of Different Pavement Performance Models on First-Class Roads with Selected Repair Technology

Faculty of Civil Engineering, University of Zilina, 010 26 Zilina, Slovakia
*
Author to whom correspondence should be addressed.
Submission received: 22 September 2021 / Revised: 29 October 2021 / Accepted: 1 November 2021 / Published: 5 November 2021

Abstract

:
Mathematical expression of the deterioration of individual pavement parameters is, from the point of optimal repair and maintenance strategy decision-making process, an important part of the application of any pavement management system (PMS). The reliability of individual PMS depends on the quality of the inputs and the reliability of its internal sub-systems; thus, deterioration equations derived from high-quality input data play pivotal roles in a system for the prediction of the pavement life cycle. This paper describes the application of pavement performance models within pavement life cycle analysis (LCA) with the use of the integrated system of economic evaluation (ISEH), which is a calculation tool used for first-class roads with a standardized pavement composition of asphalt binders, where changes in operational capability parameters are modeled using individual model simulations. The simulations presented in this paper demonstrate changes in main economic indicators (net present value and internal rate of return) on two different pavement performance models. Both simulations share the same input parameters (traffic intensity, construction intervention, maintenance costs, discount rate) but differ in deterioration evaluation, all of which were applied to each model (a total of five models).

1. Introduction

The objective of this study was to evaluate the economic impact of the application of different equations for pavement performance models. The impact of pavement performance models on repair technology and timing is well known [1]; however, there are other economic implications beyond repair technology costs linked to the road user [2]. This paper presents the sensitivity of road user costs and subsequent results of life cycle cost analysis (LCCA) and cost–benefit analysis (CBA) to even small changes in pavement performance models.
In addition, a practical method for deriving such pavement performance models is described. This method uses the synergy between accelerated pavement testing and long-term pavement performance monitoring described in separate sections.

State of the Art

Currently, practitioners understand the importance of reliable and accrued pavement performance models. The pavement management system tools and their accuracy is dependent on the accuracy of the deterioration of the selected pavement parameter. Even more so, if we consider that these tools include LCA forecast that predicts pavement deterioration based on degradation characteristic of selected parameter [3].
Following the Pavement Management Guide (second edition) [4], pavement deterioration models can be classified as deterministic, probabilistic, Bayesian, and subjective (or expert based). Uddin [5] defined three methodologies groups of performance modeling. The first group is defined as regression analysis techniques, (empirical performance models and mechanistic–empirical models). The second is defined as probabilistic performance modeling (Bayesian and Markov probabilistic modeling [6,7]) and the third group is defined as artificial neural networks modeling (back-propagation networks [8]). Nevertheless, despite the wide range of available deterioration models, the deterministic and probabilistic groups are referred to as the basic groups because they attract the greatest attention [9].
These models, which are in the line with the current state of the art of deterioration models, can be also divided into models according to the nature of the data employed for modeling; for example, Justo-Silva [10] proposed various classifications, and, according to the conceptual format, they can be divided as purely mechanistic, purely empirical and mechanistic–empirical. Most common are mechanistic–empirical methods, which are also included in design methodologies as MEPDG (Mechanistic Empirical Pavement Design Guide) from AASHTO (The American Association of State Highway Transportation) [11,12].
The state-of-the-art deterioration models of asphalt pavements combine material science by including the rheological properties of paving materials [13] with real-life pavement monitoring and experimental testing and mathematic simulations [14]. However, currently, there is a growing interest in the literature in regard to artificial neural network (ANN) models [15,16]. ANN application has increased drastically in the past few years and it is commonly used in combination with deep learning techniques. Such a combination can help address complex problems in pavement engineering [17]. Some authors regard ANN application as a “black box”, where the exact relationship between the predicted variable (dependent variable) and the independent one(s) is unknown, and hence, the real influence of each parameter cannot be known [18].

2. Deterioration Models and Model Evaluation

We present an economic comparison of two model cases (application of two different technologies, each on two selected pavement constructions) focused differently on the rut depth (RUT) parameter. Both cases have the same inputs, and the single variable is the degradation characteristic of rutting.
Based on the above-described analysis of the current state of the art in pavement operational serviceability modeling, a pavement performance evaluation method was created. This method uses deterministic modeling for which regression analysis was employed. The mathematic derivation of pavement deterioration equations was based on polynomial regression analysis from data collected on road sections through long-term pavement performance monitoring and through APT (accelerated pavement testing). This method was chosen to increase the reliability of derived pavement evolution models, which leads to a higher reliability index when compared with other methods.
The deterioration was formulated as a polynomic function of third-grade Equations (2)–(5) and polynomic function of second-grade Equation (1).

2.1. Deterioration Equations Derived from Measurements on the APT Facility

The principle of accelerated pavement testing is an application of artificially induced load applied in a short period of time on an experimentally built road section. Such facility simulates a real load on the real pavement while providing great control during the experiment, this allows researchers to evaluate different factors of road deterioration throughout the pavement life cycle [19,20].
APT is essentially a laboratory test (Figure 1) at a scale of 1:1, during which a load unit (in our case, a semi-axle of a heavy vehicle) is used to induce a load at a frequency that simulates road performance in a relatively short time, which would otherwise be distributed throughout its whole life cycle [20].
The degradation characteristics obtained experimentally were derived from data collected at the APT facility; the construction and operation parameters of the facility are presented in detail by Mikolaj et al. [21]. Derived functions from APT were already partly presented in several studies [21,22]. This paper presents the deterioration of the pavement performance index—the rut depth (RUT). International roughness index (IRI), bearing capacity, and fatigue of selected asphalt layers and their evaluation were previously presented in [22,23,24]. The RUT parameter is selected as a critical deterioration parameter for pavements with unmodified asphalt concrete surfacing.
Two deterioration models were derived from the presented APT facility. The first function was derived after 700,000 cycles of heavy vehicle simulation using Equation (1) and the second after 900,000 cycles using Equation (2). Subsequently, they were compared with other functions in order to present a total difference in economic parameters, which can arise after only 200,000 loading cycles.
The first function derived from the APT is defined by Equation (1) as follows:
R U T = 0.0535 ( n N ) 2   0.9208 ( n N ) + 1
The second function derived from the APT is defined by Equation (2) as follows:
R U T = 3.8013 ( n N ) 3 + 5.5617 ( n N ) 2 2.7629 ( n N ) + 1
In both Equations, RUT is degradation parameter (a relative value of selected deterioration of RUT depth parameter, in the range from 0% to 100% deterioration); n is the number of loading at the time of evaluation; N is the number of loading when the end-of-life limit is reached.
These deterioration equations were derived from collected data by measurement with three different measurement methods [25,26]. These three measurement methods were as follows:
  • A 3D scanning method by total station Leica;
  • A 3D scanning method by 3D portable scanner Bibus;
  • Measurement of selected profiles via leveling measurement and the straightedge method [27].
At 900,000 cycles, there are no cracks on the pavement surfacing. The first parameter that met the warning level of deterioration was the RUT depth; therefore, this paper focused on RUT evolution equations.

2.2. Deterioration Models Derived from Long-Term Monitored Sections

Degradation characteristics, derived from long-term monitored sections that are a part of Slovak Road Databank, were identified by evaluating data collected by Profilograf and Linescan devices.
Road survey for long-term monitored sections was collected yearly, approximately 2 times per year. The first RUT evolution model is an average function Equation (3) from all long-term monitored sections of all first-class roads in Slovakia [28,29], with pavement construction similar to that under the APT facility.
The first function derived from long-term monitored sections is defined by Equation (3).
R U T = 1.0136 ( n N ) 3 + 0.6603 ( n N ) 2   0.6265 ( n N ) + 0.9808
where RUT is the degradation parameter (a relative value of selected deterioration of RUT parameter, in the range from 0% to 100% deterioration); n is the number of loading at the time of evaluation; N is the number of loading when the end-of-life limit is reached.
For additional comparison with the first RUT evolution model in Equation (3), we included a second and a third model derived from long-term performance monitoring on first-class roads with a heavier loaded pavement.
The second function derived from the long-term monitored section is defined by Equation (4) as follows:
R U T = 2.0655 ( n N ) 3 + 3.1888 ( n N ) 2     2.1516 ( n N ) + 1
Further, the third function derived from the long-term monitored section is defined by Equation (5) as follows:
R U T = 2.2814 ( n N ) 3 + 2.8134 ( n N ) 2     1.5315 ( n N ) + 1

2.3. Evaluation and Model Parameters

The proprietary ISEH (Integrovaný Systém Ekonomického Hodnotenia) software (Version 2.18, University of Zilina, Zilina, Slovakia, 2021) was developed at the University of Zilina. It was used as an LCCA and CBA tool of the assessment of three case study simulations; the results show the impact of performance models herein presented on economic indicators of a project. The software is currently used by Slovak Road Administration as a tool for evaluation of economic efficiency of investments in repairs and maintenance of roads, while the latest version of the software developed and launched is adapted for use by all administration of roads and highways in the Slovak Republic. All deterioration equations described in previous sections were implemented into ISEH software via Visual Studio 2019.
LCCA and CBA were carried out following the Methodic handbook for preparation of cost–benefit analysis [30,31] for review of transport projects investment in phase 2014–2020 and obtain parameters as its net present value (NPV) and internal rate of return (IRR).
Net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows over a period of time. NPV is used in capital budgeting and investment planning to analyze the profitability of a projected investment or project. NPV is the result of calculations used to find today’s value of a future stream of payments. In our case, we used income in form of user cost savings and outcome in form of investment costs. User costs consist of operational costs (as fuel and spare part consumption), travel time loss (effect of speed reduction), and costs of accidents.
N P V = t = 1 T R t ( 1 + i ) t
where i is the discount rate (in our case 5%), Rt is net cash inflow–outflows during a single period of time (mainly user costs), T is the number of time periods (analysis of 10-year period), and t is the year of the analysis.
Internal rate of return (IRR) is a metric used in financial analysis to estimate the profitability of potential investments. IRR is a discount rate that makes the NPV of all cash flows equal to zero in a discounted cash flow analysis.
0 =   N P V = t = 1 T C t ( 1 + I R R ) t C 0
where Ct is net cash inflow during the period of time, C0 is total initial investment costs, IRR is the internal rate of return T is the number of time periods, and t is the year of the analysis.

3. Functions and Calculation Model

In the initial phase, the most accurate functions were implemented into the ISEH software source code. Based on this correlation, the following waveforms of individual parameters were created, suitable for implementation into the ISEH software environment:
The shape of each of the performance equations is different (Figure 2), and therefore, taking into account the variance, it was necessary to model changes in individual variables in the software environment and monitor their impact on the resulting values of economic indicators. The whole impact analysis in ISEH consists of five alternative performance equations and their final comparison. For the incorporation of deterioration functions into the ISEH via Visual Studio 2019 platform, it is necessary to transform Equations (2)–(6) into values from 0 to 1, in our case, via mathematical recalculation shown in Table 1.

Limited Conditions of the Computational Model

The economic impact of the rut depth (RUT) parameter was assessed for values according to the operational capability stage classification following the currently valid legislation [32] considered for first-class roads. For each category, a maximal RUT depth was specified with values of 5, 10, 15, and 25 mm. Stage one and two of classification allow a maximal RUT depth after 5 years from construction takeover, which is the warranty period of new constructed or a repaired road (maximal RUT after 5 years from the takeover of new or reconstructed construction is 10 mm). Any first-class road with a RUT depth value above 15 mm has to be assigned to the warning stage and has to be fitted with warning traffic signs (i.e., “Beware of Surface Roughness”), and maximum speed needs to be reduced from 90 km/h to 60 km/h. If above 25 mm, the RUT depth parameter of the selected road has to be considered unsuitable for road traffic. Such pavement is considered a repair priority for road administration.
This classification was chosen to compare the economic indicators of pavement sections at the same level of operational capability. The reference period was considered to be the period at which the pavement is in operation; during this time, the pavement is maintained and produces road user benefits.
The following two model simulations were used:
1
Experimental model for section A:
-
RUT parameter = 25 mm RUT depth (emergency degradation stage);
-
Required construction costs for repair technology = EUR (euro) 17,000 (milling and replacing with new layer);
-
Maintenance in the 6th year of pavement operation = EUR 1700;
-
Annual average daily traffic = 1250 vehicles in one direction per hour, of which 250 are heavy vehicles, and with annual traffic growth of 2.00%;
-
Five different performance Equations (1)–(5) were tested on experimental model A.
2
The experimental model for section B:
-
RUT parameter = 25 mm RUT depth (emergency degradation stage);
-
Required construction costs for repair technology = EUR 50,845.55 (milling and replacing with new layer);
-
Maintenance in the 6th year of pavement operation = EUR 3600.00;
-
Annual average daily traffic = 13,000 vehicles in one direction per hour, of which 1430 are heavy vehicles, and with annual traffic growth of 1.42%;
-
Five different performance Equations (1)–(5) were tested on experimental model B.
A discount rate of 5% and repaired pavement section with a life expectancy of 10 years were applied for both models.
These models were selected to observe the impacts of rutting evolution functions for pavement sections with different construction under different traffic loads.

4. Results of Economic Evaluation on Selected Alternatives of Model Sections

4.1. Parameter–Cumulative Cash Flow

In both model simulations, the repair technology was applied in the emergency degradation stage (RUT depth of 25 mm). Simulations had different repair costs. The reference period of economic analysis was 10 years (2021–2031). In both cases, performing maintenance repair action was simulated for the year 2027, i.e., the 6th year of pavement operation. In each year cumulative cash flow of the project was calculated following Equation (8). The cumulative cash flow is influenced by pavement degradation given by individual deterioration equations. Figure 3 and Figure 4 show how different deterioration equations influence cumulative cash flows in both model simulations.
The cumulative cash flow is calculated according to Equation (8) as follows:
C F c u m u l ,   n = C F c u m u l ,   n 1 + A F C n + R U B T T , n + R U B V O , n + R U B S , n
where CFcumul,n is a cumulative cash-flow in year n, CFcumul,n-1 is a cumulative cash flow in the previous year, AFCn is road administration financial spending on given section in year n (the majority being maintenance), RUBTT,n values are road user benefits for travel time in year n, RUBVO,n values are road user benefits from vehicle operation in year n, and RUBS,n values are road user benefits from increased safety in year n.

4.2. Parameter User Benefits during the Pavement Repair Life Cycle

The benefits of road users due to pavement repairs can be defined as the expression of profit directly for users (drivers, passengers, goods transport, etc.) in the form of a monetary assessment of the reduction of vehicle operating costs and shortening travel times over the period (i.e., 10 years) in a “Take some action” scenario.
Any road user benefits are calculated according to Equation (9) as follows:
R U B i , n = R U C i , n , D N + R U C i , n , D S
where RUBi,n values are road user benefits of type i (travel time, vehicle operation or safety) in year n, RUCi,n,DN values are road user cost of type i in year n for scenario “Take no action” (routine maintenance) and RUCi,n,DS values are road user costs of type i, in year n, for scenario “Take some action” (repair, reconstruction, modernization, etc.).
R U C i , n , j , R U T = j , z R E S z , n , j , R U T · U C z , j
where RUCi,n,j,RUT = x values are road user costs of type i (travel time, vehicle operation or safety) in year n of vehicle type j (personal car, bus, articulated truck, etc.) at RUT parameter value; z is the resource type (travel time hour, liter of fuel, tire wear, etc.); RESz,n,j,RUT is the resource consumption of type z in year n of vehicle type j at RUT parameter value; UCz,j is the unit cost (in EUR, GBP, USD, etc.) of resource type z and vehicle type j.
Calculation of resource consumption related to pavement degradation can range from very simple expert-based averages to complex mechanistic–empirical calculation models. ISEH uses empirical indexing of increase in resource consumption for different levels of pavement distress. An example of such indexing is shown in Table 2:
The only variable is the performance equation of RUT, ceteris paribus, the difference of cumulative cash flow is produced by the different RUT parameter forecast of evaluated deterioration models. Different RUT values produce different resource consumptions, leading to an increase in road user costs, which, in turn, lead to road user benefits; these produce positive cumulative cash flows. In the first year of the analysis, i.e., 2021, the user benefits equaled 0, i.e., there were no benefits from pavement user repairs; this value is not be stated in the graphs. The user benefits have the same shape as the deterioration equation, as it is the only variable in this comparison. This translates to the calculated cash flow. Annual user benefits for a repair at the RUT value are shown in Figure 5 for model A, and in Figure 6 for model B.

4.3. Parameter of Internal Rate of Return (IRR) during the Pavement Repair Life Cycle for Model A

As shown in previous sections, road degradation expressed with the RUT parameter can produce different benefits and resulting cash flows. The cash flow as a result of CBA can be expressed in economic terms by economic indicators. The key economic indicator we used is IRR, as it provides a good perspective on potential future cash flows. Figure 7 shows the dependency of IRR on the RUT parameter. The RUT value means the RUT parameter value at the time of repair. The IRR value shows how the economic result of such repair after 10 years of cash flows is calculated as described in previous sections. For instance, if we repair the pavement at RUT = 6 mm, we use pavement deterioration model related to Equation (2), we calculate cash flows for 10 years of operation of the repaired pavement—the resulting IRR would be −19.3%. Figure 8 shows that performing the repair too early, will lead to economically inefficient repair. It is worth noting that, in practice, an earlier repair would also require cheaper repair technology, but that was not the focus of this analysis. Repair costs were fixed, as we aimed to study the impact of the deterioration model as the single variable and adhered to “the ceteris paribus principle”.
The impact of different performance models used for the calculation of cash flows and subsequent IRR calculation is very high. Using the function related to Equation (3) for repair at the end of the pavement life cycle (RUT = 25 mm) produces an IRR of 35%, whereas using the function related to Equation (1) produces an IRR of 25.5%. This leaves a 9.5% interval of uncertainty that can influence road administration decision making. These differences are also shown in Figure 8.
Based on Figure 7, we can derive functions to describe the correlation between the rut parameter at which the repair action is performed and economic effectiveness, i.e., IRR indicator. Each of the derived functions corresponds to the equation described in Section 2 that was used in the LCCA for which the IRR was calculated. The respective equations are as follows:
The correlation between IRR and rut parameter evolution following Equation (1):
IRR = 9.10−5 rut3 − 0.0046 rut2 + 0.0991 rut − 0.7095
The correlation between IRR and rut parameter evolution following Equation (2):
IRR = 0.0001 rut3 − 0.0073 rut2 + 0.1372 rut − 0.8217
The correlation between IRR and rut parameter evolution following Equation (3):
IRR = 8.10−5 rut3 − 0.004 rut2 + 0.0882 rut − 0.5715
The correlation between IRR and rut parameter evolution following Equation (4):
IRR = 0.0002 rut3 − 0.0077 rut2 + 0.1446 rut − 0.8918
The correlation between IRR and rut parameter evolution following Equation (5):
IRR = 0.0002 rut3 − 0.0077 rut2 + 0.1448 rut − 0.8348
where IRR is the internal rate of return (%) and rut is the rut depth (mm) at which the repair action was performed.
For all heretofore presented polynomial functions resulting from the model calculation of the internal rate of return, it was confirmed that the correlation depending showed nearly perfect reliability. The original assumption, i.e., when evaluating repair actions, the pavement performance models have a strong influence on economic results and related road administration decision making was confirmed.

4.4. Parameter of Internal Rate of Return (IRR) during the Pavement Repair Life Cycle: Model B

In the functions related to Equations (2) and (4), the degree from the point of view of efficiency assessment does not indicate changes that would cause significant deviations in their evaluation. From this point of view, it is possible to assume the use of all functions in this model example of pavement repair on a long-term monitored section. A graphical representation of the results of economic efficiency in relation to IRR for the model example No. 2, along with their average values, is shown in Figure 9. The lowest value of IRR is reached when using the function and the average function related to Equation (2), the even degree in this case.

4.5. Parameter of Net Present Value (NPV) during the Pavement Repair Life Cycle: Model A

NPV for the pavement from the A and B model section APT (Figure 10 and Figure 11) reaches the highest value of the function related to Equation (3), at RUT = 25 mm—namely, approximately EUR 22,515, and the function related to Equation 4, with the value NPV = EUR 13,181. The remaining functions, defined in Equations (1), (2), and (5), reach the value of NPV in the range between these two functions. Obviously, these are significant differences for each of the selected functions, which are due to their mathematical expression. The processing range for rut depth is at least 2 mm because none of the economic indicators could be determined below this RUT value. As with IRR and rut parameter relation, the same principle can be applied to find functions describing the correlation between the rut parameter at which the repair action was performed and economic effectiveness expressed with the NPV indicator. Each of the derived functions corresponds to the equation described in Section 2 that was used in the LCCA for which the NPV was calculated. The respective equations are as follows:
The corelation between NPV and rut parameter evolution following Equation (1):
NPV = 1.1425 rut3 − 48.539 rut2 + 1970.7 rut − 23,355
The corelation between NPV and rut parameter evolution following Equation (2):
NPV = 1.2562 rut3 − 53.368 rut2 + 2166.7 rut − 23,861
The corelation between NPV and rut parameter evolution following Equation (3):
NPV = 1.4701 rut3 − 62.455 rut2 + 2535.7 rut − 24,813
The corelation between NPV and rut parameter evolution following Equation (4):
NPV = −0.8953 rut3 + 39.409 rut2 + 937.95 rut − 20,179
The relation between NPV and rut parameter evolution following Equation (5):
NPV = −1.1022 rut3 + 48.515 rut2 + 1154.7 rut − 20,620
where NPV is the net present value (EUR), and rut is the rut depth (mm) at which the repair action was performed.

4.6. Parameter of Net Present Value (NPV) during the Pavement Repair Life Cycle: Model B

Both in the course of IRR and NPV, changes in the variance of the monitored indicator of economic efficiency can be observed (Figure 12). The lowest NPV indicators, in this case, are achieved when using the function related to Equation (1), and the highest when using the function related to Equation (3). The function that is closest to the average IRR value is related to Equation (2).

5. Discussion

All performance models presented here were established with scientifically proven methods. Thorough understanding of observed pavement construction, thorough measuring methods, and sampling frequency, all prerequisites for establishing pavement deterioration models were met. The nature of APT and long-term pavement monitoring produces evolution curves of similar shapes, reflecting the familiar degradation initiation and progression phase. In this sense, the presented deterioration equations are all valid. The main variation is the “steepness” of the progress. As demonstrated, these changes may seem negligible at first glance, but in reality, when incorporated in the PMS, they produce significant aberration in economic results. Road administration decision making is usually heavily influenced by, if not completely dependent on, project economic indicators. In this sense, errors in deterioration models translate into faulty decision making. Wrong projects can be chosen at the wrong time, producing sub-optimal repair planning and economic loss to society. This is shown in Table 3, in which the breaking point of project effectiveness fluctuates with different evolution equations used for the calculation.
-
ATP functions related to Equations (1) and (2): In the economic efficiency analysis, these functions are very similar, producing similar economic results when used in the CBA. In model simulation A (average traffic load), the IRR variation interval is 0.6%. In model simulation B (heavy traffic loaded), IRR variation is 0.19%. NPV variation for model simulations A and B is EUR 2336 and EUR 8052, respectively. Thus, the IRR difference is negligible (less than 1%). However, if the decision is based on NPV in model simulation B, the variation produced by different performance models will be 25.41%.
-
Functions related to Equations (3)–(5): These equations, derived from Long-term pavement monitoring of pavements in operation, are also similar for both model simulations. For model A, the IRR variation ranges from 1.7% to 7.8%, and for NPV, from EUR 2068 to EUR 9334. For model simulation B, IRR variation ranges from 4.41% to 6.07% and NPV from EUR 16,000 to EUR 21,509. As in ATP functions, this variation is in line with the assumption that change in deterioration models can have a considerable impact.

6. Conclusions

Considering the evaluated data, we can draw the following conclusions: IRR is a more suitable economic indicator, as it is more resilient to variations produced by pavement performance models.
If the road administrator has access to more than one pavement performance model for a particular pavement parameter, he should follow one of these three approaches:
  • Use of a performance model that is most suitable for the evaluation of particular pavement sections—if the road administration has access to several deterioration equations for the same parameter, he can add additional levels of classification (classification by climatic conditions, pavement layer thickness, pavement equivalent modulus of elasticity, bearing capacity, etc.). He can then use functions that most truly represent evaluated pavement sections.
  • Picking the best functions based on reliability (most information on pavement construction, traffic loading, high measurement frequency, etc.)—the road administration should pick the most reliable function and use it in all his economic evaluations; thus, any errors and aberrations from a real-time application will copy themselves evenly into all economic analysis results. This lowers the uncertainty by preventing advantages to some projects while handicapping other projects. This will ensure a valid precedency of priority and order of projects in the repair action plan.
  • The average function–multiple deterioration equations of one parameter can be used to calculate an average deterioration equation; this has all the benefits of the second approach described above and is best used if the best function can be reliably identified.

Author Contributions

M.K. drafted and wrote the manuscript, Ľ.R. lead the APT research an coordinated the research team, M.Ď. performed in-situ measurements and collected the necessary data; Š.Š. performed LCCA for both evaluated models; J.Š. provided rheological analysis of paving materials and performed fatigue testing necessary for APT, P.D. contributed to the final manuscript with, V.H. contributed to the final manuscript and provided spelling and grammar corrections. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Main part of the data used in this study can be found in cited publications. Part of the data is available on Slovak Road Administration databank on: https://www.cdb.sk/en/ (accessed on 10 October 2021). The data presented in this study are also available on request from the corresponding author.

Conflicts of Interest

The authors declare no conflict of interest. The funders had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript, or in the decision to publish the results.

References

  1. Lee, Y.H.; Mohseni, A.; Darter, M.I. Simplified pavement performance models. Transp. Res. Rec. 1993, 1397, 7–14. [Google Scholar]
  2. Okte, E.; Al-Qadi, I.L.; Ozer, H. Effects of Pavement Condition on LCCA User Costs. Transp. Res. Rec. J. Transp. Res. Board 2019, 2673, 339–350. [Google Scholar] [CrossRef]
  3. Pérez-Acebo, H.; Gonzalo-Orden, H.; Findley, D.J.; Rojí, E. Modeling the international roughness index performance on semi-rigid pavements in single carriageway roads. Constr. Build. Mater. 2021, 272, 121665. [Google Scholar] [CrossRef]
  4. American Association of State Highway and Transportation Officials (AASHTO). Pavement Management Guide, 2nd ed.; American Association of State Highway and Transportation Officials: Washington, DC, USA, 2012. [Google Scholar]
  5. Fwa, T.F. (Ed.) Pavement management systems. In The Handbook of Highway Engineering; Taylor & Francis: Boca Raton, FL, USA, 2006. [Google Scholar]
  6. Abaza, K.A. Back-calculation of transition probabilities for Markovian-based pavement performance prediction models. Int. J. Pavement Eng. 2014, 17, 253–264. [Google Scholar] [CrossRef]
  7. Abaza, K.A. Empirical-Markovian model for predicting the overlay design thickness for asphalt concrete pavement. Road Mater. Pavement Des. 2017, 19, 1617–1635. [Google Scholar] [CrossRef]
  8. Alatoom, Y.I.; Obaidat, T.I.A.-S. Development of pavement roughness models using Artificial Neural Network (ANN). Int. J. Pavement Eng. 2021, 1–16. [Google Scholar] [CrossRef]
  9. Pérez-Acebo, H.; Linares-Unamunzaga, A.; Rojí, E.; Gonzalo-Orden, H. IRI Performance Models for Flexible Pavements in Two-Lane Roads until First Maintenance and/or Rehabilitation Work. Coatings 2020, 10, 97. [Google Scholar] [CrossRef] [Green Version]
  10. Justo-Silva, R.; Ferreira, A.; Flintsch, G. Review on Machine Learning Techniques for Developing Pavement Performance Prediction Models. Sustainability 2021, 13, 5248. [Google Scholar] [CrossRef]
  11. American Association of State Highway and Transportation Officials(AASHTO). Mechanistic-Empirical Pavement Design Guide: A Manual of Practice (Interim Edition); American Association of State Highway and Transportation Officials (AASHTO): Washington, DC, USA, 2008. [Google Scholar]
  12. Li, Q.; Xiao, D.X.; Wang, K.C.P.; Hall, K.D.; Qiu, Y. Mechanistic-empirical pavement design guide (MEPDG): A bird’s-eye view. J. Mod. Transp. 2011, 19, 114–133. [Google Scholar] [CrossRef] [Green Version]
  13. Martinez, F.; Angelone, S.; Casaux, M. Evaluation of predictive models for the rheological properties of paving asphalt binders. In Proceedings of the 6th International Conference “Bituminous Mixtures and Pavements”, Thessaloniki, Greece, 12–14 June 2019; pp. 65–71. [Google Scholar]
  14. Abdelaziz, N.; El-Hakim, R.T.A.; El-Badawy, S.M.; Afify, H.A. International Roughness Index prediction model for flexible pavements. Int. J. Pavement Eng. 2018, 21, 88–99. [Google Scholar] [CrossRef]
  15. Sollazzo, G.; Fwa, T.; Bosurgi, G. An ANN model to correlate roughness and structural performance in asphalt pavements. Constr. Build. Mater. 2017, 134, 684–693. [Google Scholar] [CrossRef]
  16. Gong, H.; Sun, Y.; Shu, X.; Huang, B. Use of random forests regression for predicting IRI of asphalt pavements. Constr. Build. Mater. 2018, 189, 890–897. [Google Scholar] [CrossRef]
  17. Kurian, A.; Sunildutt, E. Artificial Neural Networks in Pavement Engineering: A Recent Review. AIJR Proc. 2021, 11, 553–558. [Google Scholar] [CrossRef]
  18. Hugo, F.; Martin, A.E. Significant Findings from Full-Scale Accelerated Pavement Testing: A Synthesis of Highway Practice; NCHRP Synthesis; Transportation Research Board: Washington, DC, USA, 2004; ISBN 978-0-309-06974-8. [Google Scholar]
  19. Pérez-Acebo, H.; Gonzalo-Orden, H.; Findley, D.J.; Rojí, E. A skid resistance prediction model for an entire road network. Constr. Build. Mater. 2020, 262, 120041. [Google Scholar] [CrossRef]
  20. Remek, L.; Mikolaj, J.; Skarupa, M. Accelerated Pavement Testing in Slovakia: APT Tester 105-03-01. Procedia Eng. 2017, 192, 765–770. [Google Scholar] [CrossRef]
  21. Mikolaj, J.; Pepucha, Ľ.; Zgútová, K.; Remek, Ľ. Accelerated pavement testing at University of Žilina. Int. J. Eng. Technol. 2013, 5, 402–405. [Google Scholar] [CrossRef] [Green Version]
  22. Mikolaj, J.; Remek, L.; Kozel, M. Optimization of Life Cycle Extension of Asphalt Concrete Mixtures in regard to Material Properties, Structural Design, and Economic Implications. Adv. Mater. Sci. Eng. 2016, 2016, 6158432. [Google Scholar] [CrossRef] [Green Version]
  23. Schlosser, F.; Sramekova, E.; Šrámek, J. Rheology, Deformational Properties and Fatigue of the Asphalt Mixtures. Adv. Mater. Res. 2014, 875–877, 578–583. [Google Scholar] [CrossRef]
  24. Šrámek, J. Stiffness and Fatigue of Asphalt Mixtures for Pavement Construction. Slovak J. Civ. Eng. 2018, 26, 24–29. [Google Scholar] [CrossRef] [Green Version]
  25. Slabej, M.; Kotek, P. Using of 3D Road Surface Model for Monitoring of Transverse Unevenness and Skid Resistance. Procedia Eng. 2014, 91, 475–480. [Google Scholar] [CrossRef] [Green Version]
  26. Slabej, M.; Grinč, M.; Kotek, P.; Kováč, M.; Decky, M. Utilization of Advanced Diagnostic Methods for Texture and Rut Depth Analysis on a Testing Pavement Section. Civ. Environ. Eng. 2015, 11, 21–28. [Google Scholar] [CrossRef] [Green Version]
  27. Chen, D.-H.; Bilyeu, J.; Walker, D.; Murphy, M. Study of Rut-Depth Measurements. Transp. Res. Rec. J. Transp. Res. Board 2001, 1764, 78–88. [Google Scholar] [CrossRef]
  28. Slabej, M. Degradation Functions of Transverse Irregularities of Asphalt Roads. Ph.D. Thesis, University of Žilina, Žilina, Slovakia, 2012. [Google Scholar]
  29. Celko, J.; Kovac, M.; Decky, M. Analysis of selected pavement serviceability parameters. Commun. Sci. Lett. Univ. Žilina. 2011, 13, 62. [Google Scholar]
  30. Boardman, A.; Greenberg, D.; Vining, A. Cost-Benefit Analysis; International Edition; Pearson Education Limited: Cranbury, NJ, USA, 2011. [Google Scholar]
  31. Methodical Handbook for Prepare of Cost Benefit Analysis (CBA) for Review of Transport Projects Investment in Phase 2014–2020, version 2.0; Ministry of Transport and Construction of the Slovak Republic: Bratislava, Slovakia, 2017.
  32. Technological Standards. Measurement and Evaluation of Pavement Roughness—Tp 056. Ministry of Transport and Construction of the Slovak Republic, Section of Road Transport and Roads. 2012. Available online: https://www.ssc.sk/files/documents/technicke-predpisy/tp/tp_056.pdf (accessed on 3 November 2021).
Figure 1. APT facility (left); rutting on the pavement test section under the APT facility (right).
Figure 1. APT facility (left); rutting on the pavement test section under the APT facility (right).
Applsci 11 10409 g001
Figure 2. Degradation functions of RUT implemented into ISEH program environment, where RUT is a relative value of selected degradation function, i.e., rut depth; n—number of loading at the time of evaluation; N–number of loading when the end-of-life limit is reached.
Figure 2. Degradation functions of RUT implemented into ISEH program environment, where RUT is a relative value of selected degradation function, i.e., rut depth; n—number of loading at the time of evaluation; N–number of loading when the end-of-life limit is reached.
Applsci 11 10409 g002
Figure 3. Cumulative cash-flow model A.
Figure 3. Cumulative cash-flow model A.
Applsci 11 10409 g003
Figure 4. Cumulative cash-flow model B.
Figure 4. Cumulative cash-flow model B.
Applsci 11 10409 g004
Figure 5. User benefits from the implementation of the repair model A.
Figure 5. User benefits from the implementation of the repair model A.
Applsci 11 10409 g005
Figure 6. User benefits from the implementation of the repair model B.
Figure 6. User benefits from the implementation of the repair model B.
Applsci 11 10409 g006
Figure 7. Resulting values of modeling of RUT parameter changes in relation to IRR for model A.
Figure 7. Resulting values of modeling of RUT parameter changes in relation to IRR for model A.
Applsci 11 10409 g007
Figure 8. Internal rate of return for model A.
Figure 8. Internal rate of return for model A.
Applsci 11 10409 g008
Figure 9. Internal rate of return for model B.
Figure 9. Internal rate of return for model B.
Applsci 11 10409 g009
Figure 10. NPV–RUT relation for model A.
Figure 10. NPV–RUT relation for model A.
Applsci 11 10409 g010
Figure 11. NPV for model A.
Figure 11. NPV for model A.
Applsci 11 10409 g011
Figure 12. NPV for model B.
Figure 12. NPV for model B.
Applsci 11 10409 g012
Table 1. Mathematical recalculation of performance equations values.
Table 1. Mathematical recalculation of performance equations values.
Equation0.10.20.30.40.50.60.70.80.9
Equation (1)0.9070.8140.7190.6230.5260.4280.3290.2290.128
Equation (2)0.7760.6390.5690.5410.5340.5230.4870.4030.247
Equation (3)0.9240.8740.8250.7710.7060.6240.5180.3830.213
Equation (4)0.8150.6810.5860.5170.4630.4110.3480.2620.141
Equation (5)0.8730.7880.7320.6920.6520.6010.5240.4070.237
Maximal value0.9240.8740.8250.7710.7060.6240.5240.4070.247
Minimal value0.7760.6390.5690.5170.4630.4110.3290.2290.128
Table 2. Indexing of increase in resource consumption.
Table 2. Indexing of increase in resource consumption.
Passenger Car
Gradient [%]Curvature [deg/km]RUT [mm]FuelOilTravel TimeTiresSpare PartsMaintenance
00<5111111
101.021.331.081.461.981.45
251.091.671.271.923.932.15
Heavy Lorry
Gradient [%]Curvature [deg/km]RUT [mm]FuelOilTravel TimeTiresSpare PartsMaintenance
00<5111111
101.031.111.221.041.561.26
201.141.221.811.082.121.48
Table 3. Breakin point values of repair efficiency in the application of individual deterioration evolution characteristics.
Table 3. Breakin point values of repair efficiency in the application of individual deterioration evolution characteristics.
RUT Calculated by2345678910111213141516171819202122232425
Equation 1IneffectiveEffective
Equation 2IneffectiveEffective
Equation 3IneffectiveEffective
Equation 4IneffectiveEffective
Equation 5IneffectiveEffective
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Kozel, M.; Remek, Ľ.; Ďurínová, M.; Šedivý, Š.; Šrámek, J.; Danišovič, P.; Hostačná, V. Economic Impact Analysis of the Application of Different Pavement Performance Models on First-Class Roads with Selected Repair Technology. Appl. Sci. 2021, 11, 10409. https://0-doi-org.brum.beds.ac.uk/10.3390/app112110409

AMA Style

Kozel M, Remek Ľ, Ďurínová M, Šedivý Š, Šrámek J, Danišovič P, Hostačná V. Economic Impact Analysis of the Application of Different Pavement Performance Models on First-Class Roads with Selected Repair Technology. Applied Sciences. 2021; 11(21):10409. https://0-doi-org.brum.beds.ac.uk/10.3390/app112110409

Chicago/Turabian Style

Kozel, Matúš, Ľuboš Remek, Michaela Ďurínová, Štefan Šedivý, Juraj Šrámek, Peter Danišovič, and Vladimíra Hostačná. 2021. "Economic Impact Analysis of the Application of Different Pavement Performance Models on First-Class Roads with Selected Repair Technology" Applied Sciences 11, no. 21: 10409. https://0-doi-org.brum.beds.ac.uk/10.3390/app112110409

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop